Written answers

Tuesday, 29 July 2025

Department of Housing, Planning, and Local Government

Regeneration Projects

Photo of Thomas GouldThomas Gould (Cork North-Central, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

1499. To ask the Minister for Housing, Planning, and Local Government for an update on the timeline for each project currently proposed or completed in the north-west quarter regeneration in Cork city; the current spend to date; the original projected spend; and the current projected spend on completion of each project. [41994/25]

Photo of James BrowneJames Browne (Wexford, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The table below sets out the details on the timeline for each project currently proposed or completed in the north-west quarter regeneration in Cork city; the current spend to date; the original projected spend; and the current projected spend of each project.

PROJECT Number of units ORIGINAL PROJECTED SPEND CURRENT PROJECTED SPEND SPEND TO DATE Current STATUS: Actual Completion Date: Projected Substantial Completion Dated
CNWQR Knocknaheeny Phase 1B 29 5,315,971 7,468,126 6,104,987 Completed Q3, 2017
CNWQR Knocknaheeny Phase 2A 47 10,216,000 12,595,324.86 11,416,797 Completed Q4, 2019
CNWQR Knocknaheeny Phase 2B 38 10,125,873 15,118,062 9,787,804 On Site Q3, 2025
CNWQR Knocknaheeny Phase 1C 41 10,347,770 16,141,695 12,505,988 On Site Q3, 2025
Foyle Ave Infill and Ardmore Avenue, Knocknaheeny 2 488,733 1,055,601 837,482 Completed Q4, 2023
Ard na Rí, Pouladfuf 1 486,129 486,129 210,000 Completed Q2, 2023
CNWQR Knockaheeny Ave - Phase 3A 15 6,492,352 6,492,352 0 Stage 1 approved Q1, 2028
CNWQR Knocknaheeny Phase 3B 62 16,134,087 33,169,694 0 Stage 4 approved Q2, 2027
CNWQR - Phase 3C 12 5,274,251 5,274,251 0 Stage 1 approved Q1, 2028
ND Regen CNWQR Knocknaheeny Phase 4A 43 12,460,332 21,819,397 0 Stage 3 approved Q1, 2027
CNWQR - Phase 4C West 20 8,276,530 8,276,530 0 Stage 1 approved Q4, 2027
CNWQR - Phase 4F 22 9,843,858 9,843,858 0 Stage 1 approved Q1, 2028
CNWQR - 1D East 15 6,694,539 6,694,539 0 Stage 1 approved Q4, 2027
CNWQR - Croppy Boy Phase 1 24 6,994,139 10,718,217 0 On Site Q4, 2025