Written answers

Thursday, 17 July 2025

Department of Education and Skills

Public Private Partnerships

Photo of Albert DolanAlbert Dolan (Galway East, Fianna Fail)
Link to this: Individually | In context

588. To ask the Minister for Education and Skills to provide a list of all Public-Private Partnership projects under his remit, including project name, contract value, and start/end date since 2010; and to confirm whether any projects have been subject to cost overruns, renegotiation or early termination since 2010. [40416/25]

Photo of James LawlessJames Lawless (Kildare North, Fianna Fail)
Link to this: Individually | In context

Please see below a list of the Public Private Partnership (PPP) projects under my Department’s remit which have been delivered since 2010.



Name


Contract Value

(as at Dec 2024)



Year of Commencement


End Date


Subject to cost overruns / renegotiations / early terminations


Grangegorman Quads


604.7


2020

(contract was signed and construction commenced in 2018)


2045


Yes1


Higher Education Bundle 1


728.3


2025

(contract was signed and construction commenced in 2022)


2050


No

The Office of Government Procurement issued guidance in 2020/2021 for public authorities setting out a cost sharing mechanism to address additional costs incurred by contractors as a result of public health measures arising from the Covid-19 pandemic. This guidance was applied on the Grangegorman Quads project as the construction programme was impacted by these public health measures. In addition to the cost sharing mechanism set out above a re-profiling of Unitary Charge payments to address the construction delays experienced as a result of Covid-19 occurred.

Projected Total Cost are published on the Central PPP Policy Unit summary updates on operational PPP projects.