340. To ask the Minister for Culture, Heritage and the Gaeltacht the number of IT projects within his Department, or bodies under its aegis, which have been allocated funds in excess of €1 million in the years 2020 to date; the purpose of any projects; the initial estimate to complete for such projects; the total amount expended to date; the total estimated cost to complete; the estimated timeframe by which they expected to be completed; by project; by year; in tabular form; and if he will make a statement on the matter. [22951/25]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

My Department in its current configuration was established in September 2020.

I am advised that the following IT projects approved to proceed within my Department have been allocated funds in excess of €1 million in the period since then:

Year Name of IT Project allocated over €1m since Sept 2020 Purpose of Project Initial Estimated Completion Cost Total Expenditure to-date Total Estimated Completion Cost Estimated Project Completion
2023 Grant Management System Replacement of existing systems (OSCAR and CRM) €1,869,229 €103,616 €1,951,042 2026
Regarding the bodies under my Department’s remit, these are operational matters for the bodies themselves.