150. To ask the Minister for Education and Skills further to Parliamentary Question No. 169 of 17 September 2019, if authorisation has issued to invite tenders for the project; if so, when tenders will be invited; and if he will make a statement on the matter. [52098/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy is currently at Stage 2(b) – Detailed Design.

The Department understands that the Design Team is currently finalising the tender documentation and it is expected that this documentation will be submitted to the Department for review shortly.

However, due to the passage of time since the pre-qualification process, to select a shortlist of candidates, the Department has recently advised the school and its Design Team to run a new pre-qualification process. This can be carried out in parallel with the completion, submission and review of the finalised stage 2(b) documentation.

Upon receipt and review of the stage 2(b) documentation and the completion of the new pre-qualification process, my Department will be in contact with the Board of Management of the school regarding the progression of the project to the next stage of architectural planning, Stage 3 - tender stage.

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

151. To ask the Minister for Education and Skills further to Parliamentary Question No. 170 of 17 September 2019, if approval has now issued for the invitation of tenders for the project; and if he will make a statement on the matter. [52099/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

This building project referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.

The major building project is currently at an advanced stage of architectural planning Stage 2b – Detailed Design, which includes securing Planning Permission, Fire Certificate and Disability Access Certificate and the preparation of tender documents.

The process of Pre-Qualification of contractors to compile a shortlist of suitable candidates is now complete and the final checks on the tender documents are being carried out. The next step for this project will be progression to Stage 3 – tender stage.

In that context, the Department will shortly be in contact with the school and Design Team to update them on the further progression of this major building project.

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

152. To ask the Minister for Education and Skills further to Parliamentary Question No. 172 of 17 September 2019, if the accommodation brief has been finalised; if so, the details of same; and if he will make a statement on the matter. [52100/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Deputy will be aware that a building project for the school to which he refers is included in my Department's school building programme to be delivered as part of the National Development Plan.

The details of the accommodation to be provided at the school in question are expected to be determined shortly. My Department will be in direct contact with the school authority at that point.

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

153. To ask the Minister for Education and Skills further to Parliamentary Question No. 153 of 12 November 2019, the number of tenders received for the building project by the closing date of the end of November 2019; the estimated time it will take to review the tenders and award a contract; and if he will make a statement on the matter. [52101/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The project to which the Deputy refers is currently at tender stage. The closing date for tenders has now passed and six tenders have been returned. The Department expects that the Tender Report will be submitted by the Design Team in the coming weeks.

Subject to no issues arising, it is anticipated that construction will commence in the 1st quarter of 2020 and the project is expected to take approximately 20 months to complete.

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

154. To ask the Minister for Education and Skills further to Parliamentary Question No. 156 of 12 November 2019, when work will be completed on the project in view of the fact a contractor is now on site; and if he will make a statement on the matter. [52102/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As the Deputy is aware, the delivery of the project at Naas Community College has been devolved to Kildare and Wicklow Education and Training Board (KWETB).

Work began on site in November and it is expected that the building will be completed in August 2021.

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

155. To ask the Minister for Education and Skills further to Parliamentary Question No. 96 of 24 October 2019, if a definitive date for completion of phase 1 of the project has been given; when phase two will be completed; and if he will make a statement on the matter. [52104/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The school building project to which the Deputy refers is currently on site.

The first phase, consisting of the construction of the new 8 classroom school is due for completion in Quarter 4 2019 with handover anticipated in the coming weeks. The second phase is due for completion in Quarter 2 2020.

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

156. To ask the Minister for Education and Skills further to Parliamentary Question No. 95 of 24 October 2019, if stage one has been completed; if stage 2A has commenced; and if he will make a statement on the matter. [52108/19]

Photo of Joe McHughJoe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As the Deputy is aware, the delivery of the project for St. Farnan's Post Primary School has been devolved to Kildare and Wicklow Education and Training Board (KWETB).

The Stage 1 (preliminary design) process is ongoing and will need to be completed prior to the project commencing Stage 2A.