136. To ask the Minister for Education and Skills the progress of a building (details supplied). [41146/19]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Approval in principle for co-funding of the project was provided by the Department in 2018.
DCU appointed the design team for the Future Tech Building in Q3 2019. It is envisaged that the project will go on site in Q1 2021. The project is devolved to DCU for delivery.
Thomas Byrne (Meath East, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
137. To ask the Minister for Education and Skills the progress of the expansion of a campus (details supplied). [41147/19]
Joe McHugh (Donegal, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The F-Block extension on the DCU St Patrick’s Campus was completed in 2018.