Written answers
Thursday, 3 October 2019
Department of Health
National Children's Hospital Expenditure
Barry Cowen (Offaly, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
242. To ask the Minister for Health the cost of the children’s hospital; the estimated total cost of the project; when the project will be completed; and if he will make a statement on the matter. [40465/19]
Simon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source
I advised Government in December 2018 that the final cost of the design, build and equipment programme for which the National Paediatric Hospital Development Board is responsible for is now at €1,433 million. There has been no change to this figure advised to Government.
The construction phase of the project is underway. The main hospital is scheduled to be completed by late 2022 and, following a period of commissioning, is expected to open to patients in 2023.
No comments