Written answers
Tuesday, 5 March 2019
Department of Housing, Planning, and Local Government
Housing Policy
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
593. To ask the Minister for Housing, Planning, and Local Government the original targets for housing schemes; and the number of units delivered under each scheme to date in tabular form (details supplied) [10556/19]
Eoghan Murphy (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Data in relation to social housing targets and delivery on a local authority basis, across all delivery streams under Rebuilding Ireland, can be found on my Department's website at the following link:
The overall social housing targets set for 2016-2021, include homes to be delivered through a range of delivery mechanisms. This includes rapid build, buy and renew delivery and the repair and leasing scheme (RLS), along with all other delivery streams, which will contribute to the delivery of 50,000 homes over the lifetime of Rebuilding Ireland. It should be noted that it is a matter for individual local authorities to determine the most suitable mechanism for delivery at local level. The focus is on delivering homes, as quickly as possible, and utilising the schemes and delivery mechanisms that work best at local level.
Scheme | Published Rebuilding Ireland Target | Delivery to end 2018 |
---|---|---|
Repair and Leasing (RLS) | 3500 | 89 |
Rapid Build | 1500 | 423 |
Buy and Renew | No specific target published | 350 |
Housing Agency Acquisitions | 1,600 | 517 |
These targets and outputs must be taken in the context of overall delivery to date under Rebuilding Ireland, which at the end of 2018 was ahead of target.
Programme | Target 2016-2018 | Delivery 2016-2018 |
---|---|---|
Build | 10,429 | 11,830 |
Acquisition | 3,905 | 6,781 |
Lease | 2,825 | 2,620 |
Total | 17,159 | 21,231 |
No comments