593. To ask the Minister for Housing, Planning, and Local Government the original targets for housing schemes; and the number of units delivered under each scheme to date in tabular form (details supplied) [10556/19]

Photo of Eoghan MurphyEoghan Murphy (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Data in relation to social housing targets and delivery on a local authority basis, across all delivery streams under Rebuilding Ireland, can be found on my Department's website at the following link:

The overall social housing targets set for 2016-2021, include homes to be delivered through a range of delivery mechanisms. This includes rapid build, buy and renew delivery and the repair and leasing scheme (RLS), along with all other delivery streams, which will contribute to the delivery of 50,000 homes over the lifetime of Rebuilding Ireland. It should be noted that it is a matter for individual local authorities to determine the most suitable mechanism for delivery at local level. The focus is on delivering homes, as quickly as possible, and utilising the schemes and delivery mechanisms that work best at local level.  

SchemePublished Rebuilding Ireland Target Delivery to end 2018
Repair and Leasing (RLS)350089
Rapid Build1500423
Buy and RenewNo specific target published350
Housing Agency Acquisitions1,600517

These targets and outputs must be taken in the context of overall delivery to date under Rebuilding Ireland, which at the end of 2018 was ahead of target. 

ProgrammeTarget 2016-2018Delivery 2016-2018
Build10,42911,830
Acquisition3,9056,781
Lease2,8252,620
Total 17,15921,231