Ulster Canal Restoration Project
Brendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
541. To ask the Minister for Arts, Heritage and the Gaeltacht the stage of the proposal to restore the Ulster Canal; the funding provided in her Department estimates in 2016 for this project; when this project will proceed to the next stage; and if she will make a statement on the matter. [7592/16]
Heather Humphreys (Cavan-Monaghan, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Government approval to restore a 2.5km stretch of the Ulster Canal from the Shannon-Erne Waterway to the International Scout Centre at Castle Saunderson, Co. Cavan, was granted on 24 February 2015. The project, which comprises three work phases, is being undertaken by Waterways Ireland.
Phase 1, the site investigation work, has been completed. Phase 2, dredging of the River Finn, is in progress. I have been informed by Waterways Ireland that completion of this phase has been delayed as a result of contractual issues but that efforts to resolve these matters are ongoing. It is intended that Phase 3 of the restoration work, the construction of a new bridge and canal section, will proceed following completion of phase 2.
Waterways Ireland has an allocation of €2.7m in its 2016 budget for the Ulster Canal project. This is comprised of €1m from my Department's capital allocation to Waterways Ireland of €2.689m for 2016, with the balance coming from the organisation’s own resources.