Written answers

Thursday, 9 March 2006

Department of Communications, Energy and Natural Resources

Harbours and Piers

3:00 pm

Photo of Billy TimminsBilly Timmins (Wicklow, Fine Gael)
Link to this: Individually | In context

Question 111: To ask the Minister for Communications, Marine and Natural Resources the amount of funding allocated by his Department for marine projects including developing and renovation of piers, coastal protection works, marine development and other such developments since 1997 to date; the projects and the individual funding allocated for each; and the funding that has been committed and for what projects. [9816/06]

Photo of John BrowneJohn Browne (Wexford, Fianna Fail)
Link to this: Individually | In context

The Department provides funding for the development and renovation of harbours and piers through the fishery harbour development programme and for coastal protection works through the coast protection programme. A list of all projects funded under these two programmes since 1997 follows.

A list of projects approved so far under the fishery harbour development programme for 2006 also follows. The coast protection programme for 2006 is being drawn up at present.

FISHERY HARBOUR EXPENDITURE 1997 TO 2005
Fishery Harbour Expenditure in 1997
Location Project Grant Paid
£'s
County Cork
Courtmacsherry New Pier 101,250
Castletownbere Harbour works 205,911
Union Hall Completion of Decking 2,729.06
Ahakista Pier Extension 110,265.75
Roaring Water Bay New Pier & Slipway 105,579.75
Ardgroom New Pier & Slipway 90,000.00
County Kerry
Dingle Safety Works 54,652.35
Dingle Accident 8,982.25
Cromane Harbour works 145.85
County Clare
Liscannor Harbour works 79,141.00
County Galway
Cleggan Harbour works 80,718.00
Rossaveel Harbour works 75,501.00
Crumpan Beacon 21,972.87
Ardmore New Deck 21,120.31
Bunowen Harbour works 22,809.02
Killary Harbour Needs Study 2,202.20
County Mayo
Darby's Point Completion of Pier Extension 12,767.74
Ballyglass Harbour works 16,875.00
County Dublin
Howth FHC Harbour works 85,210.00
County Wexford
Kilmore Quay Dredging of New Quay 116,407.48
County Waterford
Dunmore East Harbour works 237,166.00
County Donegal
Killybegs Harbour works 392,788.00
Burtonport Fendering 150,000.00
Burtonport Site Investigation 41,987.00
Rathmullen Safety Works/Railing 846.65
Greencastle 106,514.07
County Louth
Clogherhead Pier Refurbishment 242,218.05
Carlingford Lough Harbour works 79,369.13
Miscellaneous Lights, Beacons etc 18,185
Fishery Harbour Works Undertaken in 1998
Location Project Grant Paid
£'s
Cork
Castletownbere New slipway, for Bere island, powerpoints, upgrade Auction Hall, resurfacing, syncrolift inspection, minor harbour works 572,732.00
Ardgroom Pier development 134,063.24
Ballycotton Dredging 64,500.00
Crosshaven Completion of pier development 76,561.79
Kealbeg Safety works 3,055.67
Donegal
Killybegs Upgrade Auction Hall, Syncrolift inspection, studies/investigations, general maintenance and upgrading works 644,776.00
Burtonport Dredging of approach channel 177,149.08
Carrickaroary Pier reconstruction 113,521.50
Greencastle Quay reconstruction 104,657.75
Kerrykeel Pier development 49,467.75
Portaleen Pier development 41,250.00
Port Arthur/ Magheragallen General repairs 10,644.00
Kerry
Cromane Site investigation 34,725.75
Dingle Pier extension 162,344.76
Portmagee Completion of works 7,103.84
Sneem Resurfacing of parking area 2,300.00
Blackwater Resurfacing & provision of public lighting 13,100.00
Corvagillagh Repairs to ramp and provide access at all tides 6,750.00
Knightstown remove obstruction at pier head 1,500.00
Cooncrone Improve access, provide concrete decking 6,000.00
Coonanna Repair damage at pier head 6,000.00
Louth
Carlingford Completion of pier reconstruction 40,426.43
Wexford
Kilmore Quay Dredge rock at Harbour entrance 38,749.81
Galway
Rossaveel Minor harbour works and renewals 61,022.60
Cleggan Pier repairs 741,348
Rossadilisk Pier repairs 10,780.00
Killeany General maintenance works 36,458.00
Dublin
Howth Minor works and renewals, security system, syncrolift inspection 72,763.00
Other
Galway Bay to Foyle Study 1,769.15
Piers, Lights & Beacons Various locations nationally 27,501.00
Fishery Harbour Works undertaken in 1999
Location Project Grant Paid
£'s
Wexford
Kilmore Quay Dredge rock at harbour entrance 25,131.48
Courtown Repairs to pier wall 84,000.00
Cahore Repair of slipway 15,750.00
Cork
Castletownbere Complete new slipway for Bere Island, S.I. for new pier on Dinish Island, Syncrolift carriages, minor harbour works, power points, security cameras, road rehabilitation, etc. 745,734.00
Ballycotton Repairs to breakwater 29,620.88
Knockadoon Extension to slipway 4,774.13
Durrus Extension of working area 90,428.00
Lough Beal (Pontoon) Navigation mark at entrance 8,214.31
Ballycrovane Pier development works 39,573.00
Keelbeg (Union Hall) Landscaping and surfacing entrance 30,469.00
Gerahies Pier extension/development works 53,336.00
Cape Clear (North Harbour) Repairs to outer breakwater 75,394.00
Cunnamore Pier improvements 168,281.00
Colla Pier improvements 3,649.00
Goleen Pier improvements 40,955.00
Kerry
Dingle Pier development works 334,721.00
Cromane Site investigations 12,478.89
Reen (Ballinskelligs) Widen root of pier/provide slipway 33,741.75
Portmagee Improve access and decking 19,305.29
Ballykissane Rebuild pier head/provide lighting and water 26,306.25
Rossdohan New pier and water supply 23.329.00
Knightstown New berthing wall/repairs 38,031.00
Callinafercy Pointing and repairs 2,270.00
Kilmackilogue Slipway, lifting gear & storage area 21,979.52
Clare
Doonbeg Design new pier and site investigation 38,231.00
Liscannor Completion of decking of pier 59,946.00
Seafield Stormwall and widen causeway 73,854.46
Galway
Rossaveal Provision of hardstanding and drying wall, surfacing of compound, general maintenance, car park extension and surfacing 321,830.00
Killary Harbour Design and site investigation 6,579.00
Torrea Pier, Kinvara Repair to pier/provide slipway 6,361.06
Spiddal Pier Repairs 18,750.00
Caladh Thaigh Repairs 28,295.00
Tramvarraderry (Rossaveal) Repairs 22,277.95
Ballinakill (Derryinver) Land facility 3,242.00
Cleggan Pier repairs 3,159.33
Killeany Beacon Beacon repairs and decking 26,484.00
Rossadilisk Pier repairs 17,646.00
Mayo
Darby's Point Redecking of old pier (Design) 30,754.27
Roigh Pier Parking/service area, Repairs to pier 75,000.00
Porturlin Dredge inner basin/provide mooring piles 45,000.00
Kilalla Dredge channel/silt transportation study 56,000.00
Kilcummin Remove boulders from berthage/ pier head 9,000.00
Newport Repairs to quay wall 75,000.00
Camport, Dooega Repairs to storm wall 37,500.00
Sligo
Mullaghmore Repairs 31,880.00
Raghly Pier Improve access 56,000.00
Donegal
Killybegs Pile repairs, ongoing engineering and maintenance, site investigations, pier design, new slipway, syncrolift carriages. 1,600,738.00
Greencastle Repairs to pier 376,381.52
Port na Blagh Dredging and pier furnishing 113,172.00
Woodquarter Extend and strengthen pier 176,301.54
Bruckless Replacement of furnishings/step repairs 13,239.72
Ballysaggart Reconstruct pier/breakwater and repair wall 114,003.74
Maugheragallen Extend pier — facilitate ferry and half deckers 84,969.00
Portmore Provide slipway 78,590.67
Portronan Repairs 37,145.25
Bunagee New winch/associated works including slipway 112,666.50
Moville Pier reconstruction/improvement 22,500.00
Buncrana Dredging works 33,040.50
Carrickaroary Pier repair 126,945.00
Kerrykeel Slipway 87,655.50
Waterford
Dunmore East Rehabilitation of quay structure, including remedial works to South Pier walls and east Pier stability investigation, safety, hygiene and preventative maintenance works, Shandoon cliff stabilisation study, resurfacing of harbour entrance, minor works 360,230.00
Ardmore Pier improvements 17,125.00
Dublin
Howth Resurfacing damaged areas, Provision of toilets, retaining wall stabilisation, extra carriages for syncrolift, revetment repair, replace water mains, minor works and renewals 572,623.00
Dublin
Piers, Lights and Beacons Various locations nationally 10,712.00
Fishery Harbour Works undertaken in 2000
Location Project Grant Paid
£'s
Cork
Castletownbere Effluent treatment facility upgrade, Dinish Bridge remedial works, Dinish Wharf Ext. and Auction Hall, mainland quay rehabilitation, security cameras, safety & maintenance works, syncrolift carriages 737,032.20
Keelbeg Safety works 43,488.53
Ballycotton Repairs to breakwater 83,184.65
Ballycrovane Pier development 2,931.23
Colla Pier improvements 80,035.70
Cunnamore Pier improvements 52,488.88
Durrus Extension of working area 86,254.96
Gerahies Pier ext./dev. Works 39,328.41
Goleen Pier improvements 64,547.99
Goleen Slipway 13,500.00
Lough Beal Navigation mark at entrance 2,014.29
Cape Clear Repairs to outer breakwater 51,548.35
Waterford
Dunmore East Cliff stabilisation works Phase 1 and 2, resurfacing of harbour entrance road, foul berth rehabilitation and East Pier investigation, safety & maintenance works 401,206.14
Ardmore Pier improvements 84,159.48
Tramore (Lady Elizabeth's Cove) Repairs to seawall 29,893.41
Dublin
Howth Watermains revetment, refurbishment of old canteen, extra carriages for syncrolift, safety & maintenance works 393,467.24
Donegal
Killybegs Steel pile repairs, new slipway, new pier development, safety and maintenance works, refurbishment of Harbour Master's residence 2,189,344.40
Greencastle Harbour development 17,512.65
Greencastle Pier Repairs 12,455.49
Ballysaggart Repairs 36,143.58
Buncrana Dredging & RNLI Berthing facility 210,776.25
Moville Pier improvements 108,341.00
Portmore Slipway/Site Investigation 88,554.00
Portnablagh Dredging 53,928.00
Bunagee New winch/associated works including slipway 39,380.25
Kerrykeel Slipway 8.789.00
Portsalon Pier maintenance 28,450.00
Lenan Site Investigation 44,358.00
Mountcharles Repointing/lighting/ dredging 187,957.00
Portronan Repairs 67,767.75
Bundoran Rock removal 151,812.75
Woodquarter Extend & strengthen pier 13,347.44
Bruckless Replacement of furnishings, step repairs 1,901.58
Galway
Rossaveel Safety & maintenance works, harbour feasibility study 72,947.30
Inishboffin Repairs of fenders and safety works 27,651.77
Spiddal Pier repairs 35,529.00
Torrea Pier Repairs, provide slipway 87,696.94
Lynch's Pier Slipway 1,637.37
Eanach Mheáin Survey 5,000.00
Céibh na hAirde Survey 1,828.43
Trá Bhán Pier and slipway 4,991.25
Cleggan Improve slipway/outer breakwater, provide boat repair/hardstanding, access to outer breakwater, dredging 54,581.00
Louth
Clogherhead Maintenance and safety works 88,022.36
Kerry
Cromane Site Investigation 147,332.14
Dingle Pier development Works 2,756,135.04
Dingle Pesca project 88,370.00
Dingle Resurfacing / Pontoons 69,987.50
Kilmackillogue Slipway, lifting gear and onshore storage area 60,788.39
Wexford
Kilmore Quay Dredging 397,018.59
Clare
Seafield Provide stormwall, widen causeway and construct slipway 154,103.41
Doonbeg Pier design work 113,250.00
Liscannor Pierhead widening to include steps 54,493.00
Mayo
Darby's Point Redecking of old pier 408,949.96
Killala Provision of slipway 7,526.81
Newport Quay Wall Safety barriers, power point, fresh water, etc. 2,598.00
Sligo
Mullaghmore Pier repairs 43,120.00
Strandhill Design work for slipway 18,150.00
Other
Piers, Lights & Beacons Various locations nationally 78,659.00
Fishery Harbours Expenditure 2001
Location Project DCMNR
â'¬
County Donegal
Killybegs Harbour Development 2,534,392.13
Greencastle Harbour Development 362,368.82
Greencastle Old Project 107.50
Ballysaggart 105.10
Woodquarter 94.19
Bundoran Pier Improvements 79,138.33
Burtonport Channel Dredging 56,523.98
Buncrana Pier Improvements 204,446.24
Mountcharles Slipway 69,904.19
Moville Pier Reinstatement 285,396.81
Portsalon Repairs to Pier Head 7,699.37
Portnablagh Quay Wall 29,246.19
Portaleen Repairs to Pier Head 45,891.99
Rosbeg Pier/Slipway Improvements 212,524.26
Casson Sound Quay Wall 43,350.29
Port Inver Study 51,776.74
Portmore Pier Extension 156,051.13
Binwee Pier Extra Width at Pier Head 83,529.16
Carrickarory & Moville SI for a proposed marina 60,162.36
Bonagee Complete Works at slipway 30,972.72
Inch Fort Geotechnical Investigation & Sediment Transportation Study 29,077.34
Portnoo Harbour Small slipway & winch/repairs to steps 4,734.85
Portnoo Harbour Hydrographic Studies & SI 55,352.68
Ballyederland Raise deck level/provide Storm wall 2,380.76
Moville/Carrickarory Sedimentology Study & Computer based wave Analysis study 9,903.96
Bundoran Pier Improvement Works (Dredging) 213,926.42
Ballyshannon Estuary Study of Bar Mouth & Boat storage area at the Mall Quay 28,340.55
Ballyshannon Estuary Parking Area 7,960.31
Bunagee Winch 9,245.92
Kerrykeel Reconstruction of Slipway 30,526.09
Ballyshannon Quay decking 51,962.76
Port Arthur Strengthening of Pier 3,013.43
County Galway 2001 expenditure
Rossaveel Harbour development/works 1,095,246.88
Killary Harbour Site Investigation 482.50
Trá Bhán Pier and slipway 20,256.59
Torrea Pier Repair work and concrete slab 11,911.91
Inishboffin 3,921.90
Maree Slipways (Lynch's Pier and Corraduff 147.29
Derryinver Interim works & Site Investigation 48,425.91
Claddagh Quay Improvements 48,210.37
Galway Piers Consultancy Study 31,743.45
Spiddal Sean Ceibh Improvements 73,078.10
Roundstone Repair and Improvements 36,616.26
Tully Pier Repairs and Improvements 102,928.32
Tír an Fhia Pier repair works 17,038.41
Ervallagh Pier, Repairs 12,438.53
Eanach Mheáin 2,704.54
Céibh na hAirde Quay Repairs 69,607.79
Cashla Pier Repair works 58,539.09
Kilbricken Rosmuc Pier repair works 10,745.82
Cleggan New berthage & access 289,289.77
County Mayo 2001 expenditure
Kilcummin Clear Berth 19,046.07
Purteen Harbour Improvement (Design) 95,230.36
Newport quay Wall Repairs 28,569.11
Saleen Belmullet Harbour Refurbishment 95,230.35
Kilsallagh Pier repair works 76,184.28
Killerduff Strengthen causeway & deck on pier 47,615.18
Dooega Rebuild Pier 165,065.95
Darbys' Point Re-Decking of old Pier 1,330.89
Killala Study 21,864.75
County Sligo 2001 expenditure
Mullaghmore Harbour Breakwater works 48,173.23
Rosses Point Pier Repairs 47,615.18
County Louth 2001 expenditure
Gyles Quay Pier deck and wall repairs 109,297.21
Clogherhead Safety Works 21,785.68
Clogherhead Cost Benefit Analysis 17,141.46
Clogherhead Surfacing of inner harbour 35,284.47
County Cork 2001 expenditure
Castletownbere Development & minor works, 2,248,948.97
Ballycrovane Pier Extension 117,576.03
Geraghies Pier Extension 340,080.93
Keelbeg Minor Works 18,935.59
Keelbeg Channel Dredging 9,523.04
Goleen Pier Improvements 29,641.51
Durrus Extension of working area 44,679.11
Cunnamore Pier improvements 40,925.70
Colla Pier Improvements 30,505.48
Cape Clear Development at North Harbour 70,062.98
Cape Clear Hydrodynamic Study 49,070.30
Kinsale Studies & investigations for Adam's Quay 76,087.92
Bantry Repairs and extension to Abbey Slipway 944.49
Knockadoon Slipway 104,848.62
County Dublin 2001 expenditure
Howth Minor works & renewals, 31,936.27
County Kerry 2001 expenditure
Dingle Pier Extension 79,582.87
Dingle Power Points 13,800.59
Dingle Hydrodynamic Study 35,238.65
Dingle Harbour Development & Safety Works 285,691.08
Kilmacalogue Improvement Works 28,672.45
Cromane Pier Development 206,657.47
Portmagee Dredging 47,615.18
Portmagee Improvements to lighting at pier 9,523.04
Portmagee New berthing face 19,046.07
Portmagee Extend boat dock area 47,615.18
Oysterbed, Sneem Renew pier fenders 14,284.55
Dromatoor, Ballyheigue Studies 33,330.62
Meenogahane New slipway/raise stormwall 60,756.97
Bunanear Slipway 40,332.91
Blackwater Removal of rock outcrop & S. I. 28,569.11
Templenoe Surfacing & Light 27,934.24
County Waterford 2001 expenditure
Dunmore East Shanoon Cliff Face Stabilisation & minor works 650,292.90
Lady Elizabeth's Cove, Repairs 3,437.22
Tramore
Dungarvan Repairs to quay walls at Davitt's Quay 152,368.57
County Wexford 2001 expenditure
Cahore Upgrading 61,899.73
Courtown Upgrading 128,560.98
Kilmore Quay Replace Buoyage 20,348.82
Kilmore Quay Dredging 405.48
County Clare 2001 expenditure
Doonbeg Pier Extension 50,473.40
Kilkee Slipway Upgrading 81,722.88
Liscannor Dredging 45,853.99
Doolin Development Options Study 49,198.86
Quilty 4,172.12
General
Lights & Beacons 35,610.52
Fishery Harbour Expenditure 2002
Location Project DCMNR
â'¬
Donegal
Killybegs FHC Harbour Development 14,796,488.73
Killybegs FHC Maintenance 363,199.58
Killybegs FHC New Slipway 95,167.22
Killybegs FHC Site Investigations 18,809.47
Killybegs FHC Construction wages 10,150.12
Killybegs FHC Purchase of Launch 50,445.11
Killybegs FHC Refurbishment of Residence 2,047.50
Killybegs FHC Fenders Blackrock Pier 38,092.14
Greencastle Harbour Development 575,550.83
Burtonport Channel Dredging 810,836.35
Burtonport Dredging 2,457.56
Buncrana Pier Improvements 549,487.26
Buncrana Berthing Facility/Dredging 17,420.34
Mountcharles Slipway 26,352.14
Mountcharles Repointing/Lighting 12,083.04
Moville Pier Reinstatement 2,374.76
Moville Slipway & Pier Improvements 4,866.56
Portsalon Repairs to pier head 11,381.71
Portnablagh Quay Wall 6,903.62
Portaleen Repairs to Pier Head 72,118.39
Portaleen Purchase of Crane 74,189.81
Portaleen Slipway 19,731.53
Casson Sound Quay Wall 42,818.33
Port Inver Study 25,767.78
Portmore Pier Extension 358,565.65
Portmore Slipway 28,262.24
Binwee Pier Extra Width at Pier Head 26,840.03
Binwee Pier Pier Improvements 25,366.95
Moville & Carrickaroary Studies 27,330.90
Bonagee Rock Removal & Storm Wall Works 34,207.91
Inch Fort Investigations 11,954.07
Portnoo Harbour Studies 65,133.26
Portnoo Harbour Slipway 289.52
Ballyshannon Estuary Study 10,946.77
Ballyshannon Estuary Quay Decking 4,691.10
Ballywhoriskey Harbour Development 63,486.90
Kerrykeel Slipway 3,730.24
Carrickaroary Structural Works 44,648.95
Bundoran Pier Improvements 28,192.91
Bundoran Study Wave Modelling 27,617.95
Bundoran Pier Improvements 750.37
Port Arthur Strengthening of Pier 125,111.00
Galway
Rossaveel FHC Minor Works & Renewals 418,499.14
Rossaveel FHC Complete Rockfill Contract 1,234,586.10
Rossaveel FHC Gear Store 208,960.46
Rossaveel FHC Purchase of launch 21,051.29
Trá Bhán Pier & Slipway 576,705.98
Tarrea Pier Repair work & concrete slab 70,956.47
Maree Slipways 389,270.19
Claddagh Quay Improvements 36,078.95
Spiddal Sean Céibh Improvements 17,546.36
Killary Site Investigation 7,901.33
Roundstone Pier Repairs & Improvements 13,570.36
Casla Widen Pier Access & Extend Pier 140,899.69
Ard Thoir, Carna Pier & Slipway 2,202.99
Ervallagh Pier Repairs & Improvements 11,424.74
Céibh Ailwee Pier Improvements 68,790.25
Dohulla Pier Improvements 16,153.13
Céibh na Phurtaigh Improvements 8,297.61
Inishboffin Pier Works 2,290.72
Dunloughan, Ardmore, Bunowen Studies 4,205.37
Eanach Mheáin Study 900.00
Crompan an Chonoch & Crompán Mór — Dredging & Access 69,998.29
Barna Improvement Works 69,713.25
Aughrasmore Pier Improvements 87,727.58
Céibh na hAirde Quay Repairs 145,800.66
Cashla Pier Repair Works 67,608.66
Clifden Harbour Harbour Works 3,659.57
Kilbricken, Rosmuc Improvements 190,208.49
Cleggan Provision of Crane 85,520.00
Derryinver Pier Repairs 11,844.00
Céibh Cashla, Derrynea Pier Improvements 101,206.00
Mayo
Purteen Harbour Improvement Design 70,825.50
Roigh Pier Work Area 18,750.00
Killala Slipway 375,000.00
Blacksod Pier Contribution to Development 375,021.82
Belmullet & Frenchport Lights & Barriers 38,250.00
County Mayo Assessment of Piers 33,000.00
Darby's Point Re-decking of Pier 14,558.91
Sligo
Mullaghmore Harbour Breakwater Works 234,750.00
Louth
Clogherhead Surfacing of inner harbour 45,046.50
Dublin
Howth FHC Maintenance works 111,290.60
Kerry
Dingle Slipway 26,896.38
Dingle Safety & Maintenance 217,752.64
Dingle Breakwater Works 128,416.60
Dromatoor, Ballyheigue Pier Improvements 208,476.74
Blackwater Removal of Rock Outcrop & SI 5,333.31
Bunanear Slipway 20,991.38
Bunanear 2001 Slipway 39,962.02
Oysterbed, Sneem Renew Pier Fenders 9,772.11
Kilmackillogue Improvement Works 21,425.92
Meenogahane New Slipway/Raise Stormwall 1,560.53
Portmagee New Berthing Face 75,870.08
Cromane Studies 44,186.21
Clare
Kilkee Slipway Upgrading 52,500.00
Cork
Castletownbere FHC General maintenance, Dinish Bridge Remedial works, Dinish Wharf extension, mainland quay Rehabilitation, Effluent treatment, 1,268,009.58
Ballycrovane Pier extension 397,058.25
Keelbeg (Union Hall) Channell dredging (Investigations) 96,686.73
Schull Pier wave wall repairs 166,621.46
Kinsale Damage repairs to Doneen Pier 88,356.98
Cunnamore Wave study 15,547.50
Gerahies Pier extension 176,596.50
Bantry Repairs & extension to Abbey slip 57,418.50
Durrus Pier extension 78,798.75
Priests Point, Ballinakilla 768.19
Castletownsend Slipway improvements 987,328.00
Cape Clear North Harbour development 228,197.00
Waterford
Dunmore East FHC Safety & maintenance, Surfacing, Dock Road/Island Cliff stabilisation, Shanoon cliff Stabilisation, security cameras, maintenance dredging 582,603.90
Dungarvan Davitt's Quay 141,238.51
Wexford
Duncannon Pier extension (Design) 143,368.17
Slade Pier Surfacing & safety works 44,729.25
Fethard Pier Reinforced concrete steps, Pointing to pier, 56,130.00
Carne Pier Installation of lighting/ Dredging & safety 35,062.00
Misc. Piers, lights & Beacons 73,882.00
Expenditure Review Value for money 5,694.73
Fishery Harbour Expenditure 2003
Location Project DCMNR
â'¬
Donegal
Killybegs FHC- Harbour development project 24,272,450.53
Killybegs FHC Safety and maintenance 293,508.43
Killybegs FHC- Construction wages 601.69
Greencastle Design work 139,431.23
Burtonport Dredging 252,960.77
Buncrana Pier improvements 21,724.95
Portaleen Repairs to pier head 17,205.95
Portaleen Purchase of crane 7,875.00
Portmore Pier extension 45,000.00
Port Arthur Strengthening of Pier 13,363.00
Galway
Rossaveel FHC Safety and maintenance 265,426.63
Rossaveel FHC Development 20,390.13
Tír an Fhia Pier repair works 200,861.49
Céibh na gCasla Widen pier access/extend pier 124,905.52
Inishboffin Repair of pier fenders 1,889.16
Trá Bhán Pier and slipway 6,662.17
Killary 34,000.00
Barna Improvement works 15,000.00
Aughrismore, Claddaghduff Pier improvements 162,000.00
Clifden Harbour Improvement works 40,000.00
Cleggan Install crane on pier 58,605.00
Cleggan 3,266.00
Derryinver Interim repairs 15,552.46
Sligo
Mullaghmore Harbour breakwater works 674,577.00
Mayo
Killala Slipway 114,393.00
Kerry
Dingle Fender repairs 4,390.89
Dingle Navigation light, add. Pontoon 12,000.00
Dingle Breakwater 8,738.45
Cromane Pier development 1,815.00
Bunanear Slipway 16,512.59
Dromatoor Pier improvement works 134,643.89
Ballyheigue
Clare
Kilkee Slipway upgrading 20,585.54
Liscannor Pier Safety works 4,805.00
Louth
Clogherhead Port Oriel design 191,642.25
Clogherhead Replace crane, provide handrails 75,000.00
Dublin
Howth FHC Safety & maintenance 106,197.64
Cork
Castletownbere FHC Safety & maintenance, Dinish Wharf extension, mainland Quay upgrading 1,114,130.49
Schull Pier wave wall repairs 62,021.65
Keelbeg Dredging works (sediment sampling) 299.47
Cape Clear Replace crane 16,335.00
Cape Clear Subsidence of Duffy's Pier 24,264.11
Cape Clear Safety & maintenance 6,104.50
Waterford
Dunmore East FHC Safety & maintenance, cliff Stabilisation: Dock Rd/Island Rd, Engage consultants, security cameras, Road surfacing 602,240.37
Wexford
Courtown Purchase of plant equipment 30,000
Misc. Piers, Lights & Beacons 39,139.25
Fishery Harbour Expenditure 2004
Location Project DCMNR
â'¬
Donegal
Killybegs Harbour Development Project 8,593,896.94
Killybegs Safety & Maintenance 270,833.33
Greencastle Harb. Dev. Project — Design/Planning 85,228.58
Ballyederland Raising deck level of pier 63,713.58
Buncrana Pier Dredging at pier 127,500.00
Mulroy Bay Navigational Aids 18,750.00
Ballyshannon Navigational Aids 37,500.00
Portsalon Remedial Works 52,500.00
Burtonport Provision of fenders 9,000.00
Portmore 885.78
Carrickaroary 604.58
Galway
Rossaveel Development 40,868.82
Rossaveel Safety and Maintenance 292,938.66
Rossaveel New storage Unit at RV-Advance Works 16,093.00
Rinville Pier, Oranmore New slipway, breakwater, pier deck 76,733.84
Kilbricken Repairs 13,625.25
Ard Thoir 734.34
Céibh na hAirde 54,557.61
Tír an Fhia 114,778.34
Derryinver 16,533.33
Mayo
Blacksod D/CRGA project 500,000.00
Newport 70.64
Clare
Ballyvaughan New slipway, Berthage clearance, pier repairs 12,224.11
Seafield, Quilty Raise storm wall, place rock armour 143,790.89
Liscannor Car Parking, surfacing & ladders 24,873.00
Doolin 1,875.50
Kerry
Dingle Dredging Site Investigations 201,026.77
Dingle Weighbridge 84,932.42
Cromane Pier Development Design Review Rd Access 62,942.86
Scraggane Survey 5,797.90
Oysterbed, Sneem Working/storage area 61,038.80
Tahilla, Sneem Pier works 81,569.08
Knightstown D/CRGA project 63,567.99
Tarbert Pier repairs 61,436.31
Reenard Slipway underpinning 30,776.44
Dromatoor, Ballyheigue Channel marking 15,364.99
Portmagee/Caherciveen Pier-Repairs to fenders/ladders 11,382.97
Sligo
Nil
Louth
Clogherhead Detailed design stage, Preparation of statutory Permissions 224,529.75
Dublin
Howth FHC Safety & maintenance 184,683.21
Cork
Castletownbere FHC Safety & maintenance Mainland quay rehabilitation, Effluent treatment upgrade, Dinish Wharf extension, Auction Hall Upgrading 1,941,042.89
Keelbeg Repairs to HI-Mast lighting and service blocks 9,928.13
Tragumna Slipway & access Road 116,844.95
Cape Clear Safety & maintenance 7,145.93
Cape Clear Harbour development 9,371.38
Cape Clear Duffy's Pier 3,037.93
Waterford
Dunmore East FHC Safety & maintenance, Harbour development, Security Infrastructure 909,257.64
Wexford
Kilmore Quay Hydrographic Survey 11,414.25
Misc. Piers. Lights & Beacons 50,466.49
Fishery Harbour Expenditure 2005
Location Project 2005 Outturn
â'¬
Donegal
Killybegs FHC Safety & maintenance 173,500.24
Killybegs FHC Harbour Development 3,590,303.87
Ballyederland Raising Deck Level of Pier 173,164.12
Dungloe Pier Construct slipway and turning circle at pier 10,982.18
Buncrana Pier Improvement works 78,000.00
Buncrana Pier Temp. Lifeboat Mooring 14,625.00
Bundoran Pier Pier Improvement Works 30,000.00
Castleport Pier Provision of electrical lighting 3,525.00
Mulroy Bay Navigation Aids 30,000.00
Portmore Pier, Malin Head Works to address siltation problem 31,095.05
Rathmullen Pier Pier Improvements 50,000.00
Tullyillion Pier Provision of electrical lighting 4,500.00
Portaleen Glengad Upgrade crane 22,500.00
Burtonport Harbour Rock Excavation 165,231.00
Galway
Rossaveel FHC Development & minor works 3,983,070.25
Blackweir Breakwater/holding tank 59.35
Rinville Pier, Oranmore New Slipway 243,610.07
Kilbricken, Rosmuc Repairs 1,785.68
Cleggan Pier extension & dredging SI and design 22,051.08
Mayo
Killala Silt Study 37,500.00
Rosmoney Preliminary Report 37,500.00
Louth
Clogherhead Port Oriel Upgrade & Extension 3,692,877.00
Sligo
Raghley Pier Upgrade 10,634.15
Dublin
Howth FHC Safety & maintenance 181,741.33
Cork
Castletownbere FHC Safety & maintenance 212,542.47
Castletownbere FHC Mainland Quay extension 147,568.04
Castletownbere FHC Effluent treatment 417,195.76
Castletownbere FHC Dinish Wharf extension & offices 1,306,995.22
Keelbeg Miscellaneous 7,040.73
Schull Relocation of services block & new lighting 1,364.88
Tragumna Slipway & access road 25,683.77
Cape Clear North Harbour development 457,660.31
Cape Clear Safety & maintenance 2,568.95
Garnish Pier Pier Improvement works 45,000.00
Clare
Ballyvaughan New Slipway 339,722.32
Ballyvaughan Repairs 8,586.16
New Quay Pier Repair 78,491.95
Doonbeg Pier Extension 51,427.42
Seafield, Quilty Repairs 15,900.11
Liscannor Harbour works 1,134.37
Kerry
Dingle Dredging works 18,941.41
Dingle Weighbridge 808.52
Tarbert Structural assessment 907.50
Cromane Pier Development 1,966.65
Tahilla Pier Improvement Works 8,174.45
Oysterbed, Sneem Working Storage Area 19,029.31
Scraggane Pier Survey of Pier 816.75
Renard Pier Study of repairs 106,798.50
Coonana Repairs 29,537.98
Kells Pier Safety Works & Concrete decking 4,243.57
Limerick
Kilteery Pier Provision of Bollards 21,742.12
Waterford
Dunmore East FHC Safety & maintenance & minor works 541,907.89
Ardmore Raising deck level of pier 47,656.86
Blackwater New Slipway 99,364.65
Wexford
Kilmore Quay Hydrographic Survey 61,936.88
Misc. Piers, Lights & Beacons 11,380.76
Fishery Harbour Programme
Location Project DCMNR Contribution
â'¬
Castletownbere FHC, Cork Dinish Wharf extension & offices 12,000,000
Castletownbere FHC, Cork Effluent treatment 700,000
Castletownbere FHC, Cork Mainland Quay 100,000
Clogherhead, County Louth Port Oriel development 4,127,451
Greencastle, Donegal Harbour development 2,400,000
Cromane, Kerry Development 200,000
Dunmore East FHC, Waterford Development 600,000
Dunmore East FHC, Waterford Repair to East Pier 300,000
Knightstown, Kerry Co-funded with DCRGA 400,000
Buncrana, Donegal Construction of breakwater 225,000
Burtonport, Donegal Harbour dredging Phase 2 585,000
Total 21,637,451
COAST PROTECTION EXPENDITURE 1997 TO 2005
1997 Coast Protection Programme
Location Project DCMNR
£
County Wexford
Rosslare Strand Aerial Survey/ Mapping of Coastline 19,494.00
Courtown Rock Revetment 41,998.00
Rosslare Maintenance 66,919.00
County Waterford
Tramore Strengthening of the clay cliffs and sand dunes and improvement works to main promenade 111,558.00
County Wicklow
Murrough Rock Armour Revetment 35,593.00
Bray Beach Nourishment/ Groyne Protection 41,717.00
Murrough Maintenance 22.00
County Sligo
Enniscrone Planting of Grass 4,735.00
Strandhill Wind Fencing 30,000.00
County Louth
Annagassan Rock Revetment 9,846.00
County Donegal
Inver Completion of Seawall 10,000.00
Rye/Rathmullan Seawall Protection 39,000.00
Teelin Seawall Protection 60,000.00
County Meath
Laytown Study 14,996.00
County Mayo
Bertra Dune Protection 41,250.00
Claggan Dune Protection 11,250.00
County Dublin
Burrow Study 15,586.00
County Cork
Glandore Seawall Protection 122,011.00
County Clare
Rinevella Coast protection 100,000
General
CZM Study
Sensitivity Study
ECOPRO Manual
1998 Coast Protection Programme
Location Project DCMNR
£
County Dublin
Burrow Study 5,387.00
County Louth
Annagassan Rock Revetment 141,004.00
County Wexford
Rosslare Aerial Survey/Mapping of Coastline 7,721.00
Rosslare Maintenance 46,636.00
County Wicklow
Bray Breakwater & Groyne 740,479.00
Murrough Rock Armour 2,682.00
1999 Coast Protection Programme
Location Project DCMNR
£
County Louth
Annagassan Detailed design of Phase 2 Protection Scheme 15,000.00
County Dublin
Vico Road Protection Works at Vico Road (Design) 10,508.85
County Wicklow
Bray Coast Protection Phase 1 385,163.75
Bray Harbour Wall Protection 234,934.50
County Wexford
Courtown Dune Protection 53,250.00
Curracloe Study for Coast management 22,500.00
Ballyconnigar Cliff Protection 75,000.00
Rosslare Strand Beach Protection Work 4,359.23
Rosetown Cliff Protection (Design) 3,774.52
Cullenstown Detailed Design for Protection Works 20,547.00
Rosslare Strand Maintenance 24,222.41
County Cork
Youghal Further Study of Protection Options 21,000.00
Roscarberry (Owennahincha) Road Protection 33,750.00
Roscarberry (Warren) Groyne 12,957.00
Barley Cove Study of Required Dune Protection Works 15,000.00
County Kerry
Waterville Protection Works 120,000.00
County Clare
Quilty Protection Works 607,989.75
County Galway
Inishboffin Island Road Protection 77,828.00
Aughinish Is. Causeway Protection 30,000.00
Roundstone Dune Re-Instatement 16,368.00
Gorteen Bay/Dogs Bay Mweeloon/ Ballynacloghy Road Protection 116,250.00
County Mayo
Claggan Is Dune Reinstatement 21,660.86
Belmullet-Elly Bay Study 17,345.00
County Sligo
Mullaghmore Road Protection 17,926.00
Strandhill Study 27,225.00
County Donegal
Bundoran Road Protection 90,000.00
Mountcharles Coast Protection 65,250.00
Inver Coast Protection 45,000.00
County Waterford
Tramore Coast Protection 25,377.15
General County Louth Coastal Survey 52,535.01
GIS Initial Set up 31,561.14
Aerial Survey V Carnsore Pt to Killiney 40,882.22
Wavebuoys 9,421.67
National Coastline Survey 10,000.00
2000 Coast Protection Programme
Location Project DCMNR
£
County Louth
Annagassan Phase 2 Protection Scheme 69,876.29
County Dublin
Vico Rd. Cliff Protection Works 30,025.66
Bull Island Study of effects of breaching the causeway 30,000.00
County Wicklow
Bray Phase 2 & Remedial Works 1,579,131.53
County Wexford
Rosslare Beach Protection 44,699.36
Rosslare Maintenance 15,480.62
Cullenstown Revetment Works & training walls 86,025.00
County Waterford
Tramore Promenade wall Strengthening 36,321.89
Cunnigar Design of Protection Works 20,910.38
County Kerry
Rossbeigh Consultancy Study 30,000
Waterville Upgrade & Road Protection 63,452.52
Dingle-Castlemain Road Rock armour 1,100,000
County Clare
Quilty Protection Scheme 159,216.75
Seafield Dune Protection Works 16,125.00
Ballyvaughan Road Protection Works 91,935.75
County Galway
Auginish Island Causeway Protection Works 46,125.00
Cleggan Beach Road Protection 77,669.80
Tawin Island Beach Road Protection 39,000.00
Gorteen Beach Beach Protection 38,250.00
Renville Coast Protection to public recreation area 39,600.75
Clifden Beach Coast Protection to public recreation area 75,375.00
Inishmore Island Beach Road 45,000.00
Oranmore/Mweeloon Road Protection Works 46,929.00
County Mayo
Achill Dune Protection Works 25,074.75
Elly Bay Seawall Repairs/Dune Protection 80,417.32
Bertra Beach Dune Protection Works 37,645.50
Fahy-Ballycroy Sea outfall renewal and Coast Protection 46,578.75
Bundoola Belmullet Repairs to seawall 15,864.75
Keel Beach Dune Protection works 14,266.50
County Sligo
Strandhill Dune Protection works 13,725.00
Mullaghmore Road Protection works 88,986.29
Pollacheeney Protection Works 54,000.00
County Donegal
Bundoran Road/Cliff Protection 233,255.25
Kerrykeel Repairs to sea wall 48,536.25
Mountcharles Rock armouring 79,621.15
Rye, Rathmullen Sea wall rock armouring 113,745.75
Inver Coast Protection 20,274.75
General Total Cost (all DCMNR)
£
Coastal Survey 35,955.99
GIS System/Maintenance 13,240.00
Wave Buoys 13,625.13
Pilot Project for dissemination 2,994.75
Research Startup 4,523.59
Coastal Survey, County Louth 1,845.29
GIS initial setup 177.13
2001 Coast Protection Programme
Location Project DCMNR
£
County Donegal
Drung, Quigley's Pt Rock Armour 207,652.65
Keadue, Kincasslagh Seawall 31,746.80
Mountcharles Road Protection Works 233,435.54
Mahery, Dungloe Road Protection Works 23,662.38
Kerrykiel, Rossakill Road Protection Works 118,048.50
Kerrykeel Sea Wall Repairs 1,645.58
Inver Concrete Slab & Low level wall 36,186.58
Carrickarory Repointing existing Seawall 3,176.88
Bundoran Shoreline Protection 87,528.52
Rye, Rathmullan Sea Wall 5,482.41
County Sligo
Strandhill Slipway 14,284.55
Strandhill Shoreline Protection 69,994.31
Mullaghmore Road Protection Wks. 385,546.76
Pollacheeny Study & Detailed Design 29,616.64
County Mayo
Westport/Bertra Dune Protection 28,569.11
Carrowmore Beach Dune Protection 19,046.07
Roonagh, Louisburg Road Protection Works 28,569.11
Belmullet Town Repair Sea Walls 95,230.36
Mulranny Causeway Protection Works 85,707.32
Bundoola, Belmullet Repairs to Seawall 75,085.96
Claggan Island Dune Protection Works 53,759.02
Elly Bay Seawall Repairs & Dune Protection 76,673.56
County Galway
Auginish Island Causeway Protection 38,092.14
Inishboffin Protection Works to south facing shore 95,230.36
Inishboffin Erosion Study of south facing shore 28,355.82
Renvyle Road Protection 47,615.18
Inishmore Airstrip Protection 8,281.87
Ballyconnelly Road Protection Works 85,707.32
Roundstone Pier Study 18,411.20
Cleggan 59.73
County Louth
Annagassan Phase 2 Protection Works 149,908.10
Salterstown Protection Works 33,454.68
County Dublin
Bull Island Study 63,880.52
County Wicklow
Bray Phase 2 Coast Protection 647,673.60
Bray Remedial Works/Extension of harbour wall 792,131.26
Bray Coast Protection Scheme 20.02
County Wexford
Courtown Revetment Works 86,899.68
Cullenstown Revetment Works 685,612.85
Rosslare Strand Study of North end of spit
Rosslare Strand Maintenance
Rosslare Strand Revetment Works 71,422.77
Rosslare Strand New Scheme 188.78
County Waterford
Ballyvoile Study of Road Protection Works 31,484.01
Tramore Promenade Wall Strengthening 880,041.04
County Cork
Durris to Ahakista Road Protection Works 66,314.61
Youghal Preparation of Tender And Planning 19,046.07
Youghal Sea Wall Repairs 28,569.11
County Kerry
R561 Dingle to Castlemain Revetment Works 1,386,430.06
County Clare
Quilty Protection Scheme 73,815.11
Clahanes Liscannor Concrete Wall 175,086.91
Rinvalla Bay Road Protection Works
Aughinish Island Causeway Protection Works 39,276.27
General
Wave Buoys 2,989.61
Aerial Survey Carnsore to Killiney 63,281.12
GIS Maintenance 2,384.52
Coastal Surveys 2001 10,240.44
GIS Maintenance & Development 33,284.28
2002 Coast Protection Programme
Location Project DCMNR Cost
â'¬
Strandhill, County Sligo Shoreline Protection 532,500
Mullaghmore, County Sligo Road Protection 67,286.25
Keadew, Kincaslagh, County Donegal Sea Wall 183,974.90
Maghery, Dungloe, County Donegal Road Protection 82,330.31
Mountcharles, County Donegal Road Protection 9,249.64
Kerrykeel, County Donegal Road Protection 1,180.65
Carrickaroary, County Donegal Repointing Existing Sea Wall 16,705.54
Drung, Quigley's Point, County Donegal Rock Armour 11.606.83
Lagg, Malin Head, County Donegal Study of Coastal Processes 23,923.18
Inver, County Donegal Protection Works 991.29
Inisboffin, County Galway Protection Works to South Facing Shore 142,875
Salin to Silverstrand, County Galway Study 79,830.46
Tawin Island, County Galway Road Protection 53,913.51
Claggan Island, County Mayo Repair Works 33,160
Bunnafolly, County Mayo Protection Works 27,108
Lacken, County Mayo Cliff/Road Study 22,500
Elly Bay, County Mayo Installation of ECAB Units 148,608
Bellurgan, County Louth Embankment Reinstatement 170,151.75
Louth Coastline Survey of Coastline 7,568.25
Whitestown, County Louth Rock Armour Protection 37,335.64
Blackrock, County Louth Seawall Protection 32,487.75
Salterstown, County Louth Repairs & Protection to Road Verge 393,617.25
Seapoint, County Louth Dune Protection Works 75,000
Blackrock to Dundalk, County Louth Study 36,300
Shelling Hill/Gyles Quay, County Louth Protection Works 34,419
Carlingford Harbour, County Louth Repairs 623.25
Annagassan Harbour, County Louth Protection Works 26,068.50
Tramore, County Waterford Promenade Refurbishment 228,194.88
Cunnigar, County Waterford Rock Revetment 244,273.60
Rosslare Strand, County Wexford Study of North End of Spit 114,435
Courtown, County Wexford Design of Breakwater 133,810.34
Rosslare Strand, County Wexford Revetment Works 77,846.49
Rosslare Strand, County Wexford Maintenance 13,292
Cahore, County Wexford Rock Groynes & Beach Nourishment 42,966.58
Ballyconnigar, County Wexford Rock Revetment 21,750
Garretstown, County Cork Road Protection Works 209,259.83
Durris to Ahakista, County Cork Road Protection Works 135,179
Warren, County Cork Beach Groynes 112,500
Youghal, County Cork Planning Stage 37,500
Ballyheigue/Inch, County Kerry Road Protection Works 414,243.46
Knightstown, County Kerry Protection Works 37,856.12
Carrigaholt, County Clare Protection Works 45,897
Shanganagh, County Dublin Study 7,482.91
Bray, Co Wicklow Pier Repair Works 440,244
Dún Laoghaire, County Dublin Vico Road Revetment 212,718.05
Portmarnock, County Dublin Dune Protection Works 37,487.86
Coastal Study Consultancy Study 2,955
Coastal Surveys General Coastal & Project Related 4,212
GIS System Customisation, Maintenance & Training 9,537
Wave Buoys Maintenance & Deployment 7,391
Beach Monitoring Monitoring of Nourished Beach, Bray 5,816
East Coast Aerial Survey — Carnsore to Killiney 21,785
Value for money Review 37,368
2003 Coast Protection Programme
Location Project DCMNR Cost
â'¬
Elly Bay, County Mayo Installation of ECAB Units 68,182.59
Devlin, County Mayo Rock Armour, Retaining Wall 60,000
Bellurgan, County Louth Embankment Reinstatement 5,736
Salterstown, County Louth Repairs & Protection of Road Verge 90,000
Carlingford Harbour, County Louth Damaged Navigational Light 2,253
Shore Road, Dundalk, County Louth Sea Defence Embankment 58,500
Blackrock, County Louth Rock Armour 40,905
Annagassan, County Louth Protection Works 6,706.50
Cruisetown, County Louth Extend coastal protection 60,738
Salterstown Pier, County Louth Protection Works 22,527.25
Drung, Quigleys Pt., County Donegal Road Protection Works 40,277.59
Meenacross, County Donegal Rebuild Portion of Wall, Repoint Wall 15,000
Muckross, County Donegal Rock Armour Revetment to Protect Public Road 60,000
Carrigaholt Castle, County Clare Protection Works to National Monument 32,661.50
Cappagh, County Clare Road Protection Works 74,700
Carrigaholt, County Clare Reconstruction of Rock Revetment 21,753
Doonbeg, County Clare Rock Armour 17,011.50
Liscannor, County Clare Rock Armour 13,710.53
Rosslare Strand, County Wexford Study 8,616.23
Rosslare Strand, County Wexford Capital Works 14,290.46
Rosslare Strand, County Wexford Maintenance 7,957.54
Rosslare, County Wexford New Scheme 155.38
Cahore, Wexford Rock Groynes, Beach Nourishment 43,286.42
Rosslare, County Wexford Revetment Works 27,821.01
Ballyconnigar, County Wexford Rock Revetment 22,239
Warren Strand, County Cork Beach Groynes 120,000
Youghal, County Cork Coastal Protection Phase, Prep. Contract Docs. 22,687.50
Warren Strand, County Cork Complete Phase 2 Groyne 41,623.31
Tramore, County Waterford Promenade Refurbishment 17,572.30
Cunnigar, County Waterford Balance of 2001 Grant 1,004.40
Dublin City Council, Dublin Risk Assessment Study 80,000
Ballyheigue, County Kerry Road Protection Works 150,000
Ballyheigue, County Kerry Complete Phase 1 225,000
Ventry, County Kerry Coastal Protection Works 21,785.48
Kenmare, County Kerry Sea Wall 11,269.77
Brittas Bay, County Wicklow Update Study, Extension of Scheme 37,351.79
Burrow, Portrane, Fingal Repairs to Embankment, etc. 7,500
Portmarnock to Malahide Fingal Repairs to Coastal Walkway 3,750
Coast Protection Strategy Study 370,471
GIS System Maintenance and Customisation 26,726
Bray Beach Monitoring 4,646
Basic Research Tide Gauge Review Statistical Analyses 19,800
2004 Coast Protection Programme
Location Project DCMNR Cost
â'¬
Inishboffin, County Galway Emergency Work 144,932.87
Laytown, Co Meath Laytown Study 30,000
Drogheda, County Louth Erosion of R167 28,986
Bellurgan, County Louth Erosion (Road) 8,226.34
Cooley, County Louth Replacement of rock armour 43,873.50
Kilfenora, County Kerry Revetment Works 117,292.49
Baile an Rannaig, County Kerry Provision of rock armour 88,090.30
Dún Laoghaire/Rathdown CC Coastal Survey 19,239
Corbawn Lane, County Dublin Contract documents, etc. 30,855
Warren, County Cork Coast Protection Works 142,848.42
Youghal, County Cork Phase 1 379,458.88
Helvick Pier, Waterford Emergency Works & Diving Survey 70,092.76
Courtown, County Wexford Design of Breakwaters, etc. 368,204.08
Curracloe, County Wexford Dune Protection 31,030.92
Greystones, Co Wicklow Coast Protection Site Investigation 52,500
Coast Protection Strategy Study 174,220.62
GIS System Maintenance & Customisation 31,389.95
Wave Buoy Maintenance & Deployment 45,188.39
Beach Monitoring Monitoring of nourished beach at Bray 16,992.27
Tide Gauge Installation of gauge for monitoring mean sea level 11,335.64
Coastal Video Survey Video Survey of national coastline 30,991.50
Rosslare, County Wexford Maintenance 83,198.63
2005 Coast Protection Programme
Location Project DCMNR Cost 2005
â'¬
Donegal
Curransport, Meenlaragh Protection works 52,500.00
Gweebarra Bends Protection to Sea Wall 30,000.00
Inver Village Extension to protection wall 52,500.00
Lagg Beach Protection works 45,000.00
Moville Green amenity area and path 4,500.00
Rosbeg Protection works 15,000.00
Rye, Rathmullen Protection works 105,000.00
*Aranmore Protection works 31,875.00
*Maghery Protection works 37,500.00
*Muckross Protection works 9,375.00
Louth
Annagassan Strand Road 28,377.27
Salterstown Road Protection works 48,193.50
Port Beach Study 11,253.00
Mayo
Bertra Beach, Westport Protection Works 75,000.00
Sligo
Mullaghmore Dune Management Scheme 11,340.75
Rathlee Coast Protection Works 31,352.88
Galway
Inishboffin Road protection Works, Design, Tenders, etc; 108,280.47
*Inishboffin Road Protection Works 75,000.00
Cork
Gyleen Village Protection Works 148,553.90
Youghal Phase 1 completion 232,892.50
Clare
Ross/Kilbaha Rock gabions & Rock revetment 88,987.50
Carrigaholt Road Protection Works 54,232.50
Kerry
Killelan Caherciveen Road Protection Works 15,000.00
Baile an Rannaig Provision of rock armour 1,968.88
*Reen Ballinskelligs Protection works 7,500.00
Maherees Road Protection Works 74,821.48
Kilfenora Revetment Works 21,100.12
Dublin City Council
Merrion Gates Provide banking/ramping to seal opening 36,386.09
Clontarf Promenade Flood Defences Detailed Design 30,219.75
Spencer Dock Sea Surge Defence Barrier 120,894.16
Dún-Laoghaire Rathdown
Killiney Repairs to Beach Gabions 109,275.00
Corbawn/Shankill Repairs to Beach Access 29,947.50
Waterford
Bunmahon Protection Works/Scheme Design 17,825.77
Cunnigar, Dungarvan Protection Scheme/Design 69,493.58
Wexford
Cahore Continuation of Revetment works 16,616.87
Kilpatrick Soft engineering Works to Beach 15,271.43
Rosslare Soft Engineering Works to Beach 10,118.96
Wicklow
Arklow South Beach 44,356.15
Bray to Greystones Cliff path works 69,665.25
Bray Promenade flood prevention wall at Bray 55,500.00
General
Coastal Protection Strategy Study 132,816.27
GIS System Customisation, maintenance and training 18,929.16
Wave Buoys Maintenance and Deployment 8,556.06
Beach Monitoring Monitoring of nourished beach at Bray, County Wicklow 4,646.40
Tide Gauge Installation of gauge for monitoring mean sea level 60,728.74
Detailed survey of selected coastal areas 41,881.85
Rosslare Maintenance 14,832.08
Miscellaneous 5,133.26

Comments

No comments

Log in or join to post a public comment.