Written answers
Wednesday, 9 November 2005
Department of Transport
Rail Network
8:00 pm
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 278: To ask the Minister for Transport the start and completion date for phase two of the Navan rail link; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33322/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 284: To ask the Minister for Transport the start and completion date for the proposed Tuam to Claremorris rail line; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33328/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 285: To ask the Minister for Transport the start and completion date for the proposed interconnector; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33329/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 286: To ask the Minister for Transport the start and completion date for the proposed electrification of rail lines to Balbriggan, Maynooth, Navan and Hazelhatch; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33330/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 292: To ask the Minister for Transport the start and completion date for the Athenry to Tuam rail line; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33336/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 298: To ask the Minister for Transport the start and completion date for the Kildare rail upgrade; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33342/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 303: To ask the Minister for Transport the start and completion date for the proposed Cork commuter rail service to Midleton; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33347/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 304: To ask the Minister for Transport the start and completion date for the proposed Ennis-Athenry rail line; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33348/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 306: To ask the Minister for Transport the start and completion date for phase one of Navan rail link; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33350/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 307: To ask the Minister for Transport the start and completion date for a proposed Docklands rail station; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33351/05]
Olivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context
Question 308: To ask the Minister for Transport the start and completion date for the proposed Portlaoise train depot; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33352/05]
Martin Cullen (Waterford, Fianna Fail)
Link to this: Individually | In context
I propose to take Questions Nos. 278, 284 to 286, inclusive, 292, 298, 303, 304 and 306 to 308, inclusive, together.
I am arranging to have all the information made publicly available at the launch of Transport 21 forwarded to the Deputy and lodged in the Oireachtas Library. For ease of reference, the completion dates identified in Transport 21 for the projects referred to by the Deputy are as follows:
Date | |
Ennis to Athenry Rail Line | 2008 |
Athenry to Tuam Rail Line | 2011 |
Tuam to Claremorris Rail Line | 2014 |
Navan Rail Link Phase 1 | 2009 |
New Docklands Rail Station | 2009 |
Navan Rail Link Phase 2 | 2015 |
Portlaoise Train Depot | 2007 |
Midleton Commuter Rail Link | 2008 |
Kildare Route Project | 2010 |
Rail Interconnector | 2015 |
Extended Rail Electrification in Dublin | 2015 |
It is not currently envisaged that any of these projects will be procured as a public private partnership. Each project will be the subject of a procurement process, but I am not prepared to give details of the costings included in Transport 21 in advance of receipt of tenders.