Written answers

Wednesday, 9 November 2005

8:00 pm

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 278: To ask the Minister for Transport the start and completion date for phase two of the Navan rail link; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33322/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 284: To ask the Minister for Transport the start and completion date for the proposed Tuam to Claremorris rail line; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33328/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 285: To ask the Minister for Transport the start and completion date for the proposed interconnector; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33329/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 286: To ask the Minister for Transport the start and completion date for the proposed electrification of rail lines to Balbriggan, Maynooth, Navan and Hazelhatch; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33330/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 292: To ask the Minister for Transport the start and completion date for the Athenry to Tuam rail line; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33336/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 298: To ask the Minister for Transport the start and completion date for the Kildare rail upgrade; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33342/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 303: To ask the Minister for Transport the start and completion date for the proposed Cork commuter rail service to Midleton; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33347/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 304: To ask the Minister for Transport the start and completion date for the proposed Ennis-Athenry rail line; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33348/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 306: To ask the Minister for Transport the start and completion date for phase one of Navan rail link; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33350/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 307: To ask the Minister for Transport the start and completion date for a proposed Docklands rail station; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33351/05]

Photo of Olivia MitchellOlivia Mitchell (Dublin South, Fine Gael)
Link to this: Individually | In context

Question 308: To ask the Minister for Transport the start and completion date for the proposed Portlaoise train depot; if this project will be a public private partnership; the estimated cost of this project; and if he will make a statement on the matter. [33352/05]

Photo of Martin CullenMartin Cullen (Waterford, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 278, 284 to 286, inclusive, 292, 298, 303, 304 and 306 to 308, inclusive, together.

I am arranging to have all the information made publicly available at the launch of Transport 21 forwarded to the Deputy and lodged in the Oireachtas Library. For ease of reference, the completion dates identified in Transport 21 for the projects referred to by the Deputy are as follows:

Date
Ennis to Athenry Rail Line 2008
Athenry to Tuam Rail Line 2011
Tuam to Claremorris Rail Line 2014
Navan Rail Link Phase 1 2009
New Docklands Rail Station 2009
Navan Rail Link Phase 2 2015
Portlaoise Train Depot 2007
Midleton Commuter Rail Link 2008
Kildare Route Project 2010
Rail Interconnector 2015
Extended Rail Electrification in Dublin 2015

It is not currently envisaged that any of these projects will be procured as a public private partnership. Each project will be the subject of a procurement process, but I am not prepared to give details of the costings included in Transport 21 in advance of receipt of tenders.