Department of Education and Skills

Schools Building Projects

Photo of Thomas GouldThomas Gould (Cork North-Central, Sinn Fein)
Link to this: Individually | In context

134. To ask the Minister for Education and Skills if she is aware of land available and owned by Cork City Council for new school buildings (details supplied) in Ballincollig, County Cork; whether officials have engaged with the council in respect of acquiring the land; and the status of new school buildings for both projects. [68175/25]

Photo of Hildegarde NaughtonHildegarde Naughton (Galway West, Fine Gael)
Link to this: Individually | In context

Cork City Council compulsory purchased lands for schools referred to by deputy on behalf of the Minister. These lands will be used for the development of a two school campus for the schools referenced.

These lands will be transferred into the Minister's name in due course. The capital project for development of these school facilities is progressing through the design and planning stages.

The project is currently at the initial stage of architectural planning – Stage 1, where a site and current building assessment is carried out, and initial design sketch schemes are created.

Currently the Programme Manager and the design team anticipate the Stage 1 Submission will be available to the Department in the coming weeks, and that the Stage 1 Stakeholders Meeting will be held before the end of December 2025.

The schools and patron body will be updated as to the progression of the project on completion of the Stage 1 review.

Photo of Thomas GouldThomas Gould (Cork North-Central, Sinn Fein)
Link to this: Individually | In context

135. To ask the Minister for Education and Skills the number of new school building projects and extensions currently underway in Cork, by stage and date the project entered that stage, including the number of pupils currently in the school, in tabular form. [68176/25]

Photo of Hildegarde NaughtonHildegarde Naughton (Galway West, Fine Gael)
Link to this: Individually | In context

Since 2020, my department has invested over €6 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,300 school building projects. In addition, repurposing and optimisation of existing accommodation capacity across the school estate has been a key enabler of timely, local provision of special class capacity in a way that supports best practice in inclusion and integration. Circa 80% of new special classes in 2025/26 are being facilitated in repurposed classroom accommodation.

Government support for this investment, including by way of supplementary capital funding, has delivered real benefits for school communities. Supplementary capital funding of €210 million approved by Government has brought the total capital allocation for 2025 for my department to €1.6 billion.

In July the Government announced a capital allocation of €7.55 billion for the Department of Education and Youth for the period 2026-2030 under the National Development Plan. A focus of this plan will be, in the first instance, to maximise the capacity of the existing school estate as much as possible. Additional capacity will be provided through targeted and prioritised projects which will be delivered over the course of 2026 to 2030 which will meet the most urgent and prioritised needs while ensuring delivery that is affordable, offers value for money, and meets functional needs.

It is planned that circa 80 school building projects will progress to construction across 2026 and 2027 as part of a 2-year rolling programme and in this context all Government departments are expected to publish their sectoral NDP Implementation Plans shortly.

The current status of all projects is set out under item number ten at the following link (www.gov.ie). This is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction.

The table below lists the school building projects currently in construction in Cork.

Roll Number School Name Townland School Level Project Type Start On Site Date Enrolments 2024-2025
00467B Ballinspittle NS Ballycatten Primary New School Q2 2024 184
04953H Ballyhass NS Ballyhass Primary Extension Q4 2024 234
12473M Greenmount Monastery NS Greenmount Primary Extension Q1 2025 237
13031I St. Joseph's Convent NS Charleville Primary Extension Q4 2024 213
14813U Roscarbery Con NS Ardagh East Primary Extension Q3 2024 111
17168J SN Inis Eoghanain Inis Eonáin Primary Extension Q2 2025 297
17362F SN Breandan Naofa Mallow Primary Extension Q4 2025 75
01692N Firmount NS Firmount Primary Refurbishment Only Q4 2025 169
10724B South Abbey NS Youghal Primary Refurbishment Only Q1 2025 221
20534C Owenabue ETNS Carrigaline Primary Refurbishment Only Q4 2024 91
01272O SN Chuan Doir Drombeg Primary Extension Q3 2025 76
14433K Abbeystrewry NS Skibbereen Primary Extension Q4 2025 139
15484J Glounthaune NS Glounthane Primary Extension Q3 2025 432
16339F SN Iosef Naofa Mardyke Walk Primary Extension Q2 2024 217
17251T Oven's NS Ovens Primary Extension Q4 2025 442
17790D Curraghagalla NS Kilworth Primary Extension Q3 2025 25
17950W Shanagarry NS Midleton Primary Extension Q3 2025 116
18567F SN Inis Killeagh Primary Extension Q2 2025 200
19232C SN Barra Naofa Cailiní Beaumont Primary Extension Q2 2025 324
19526T SN Cill Dairbhre Kildorrery Primary Extension Q4 2025 184
20009G Gaescoil Dr. M. Uí Shúilleabháin Skibbereen Primary Extension Q3 2025 78
20024C Bunscoil Muire Youghal Primary Extension Q4 2025 528
20107G Gaelscoil Mhainistir na Corann Midleton Primary Extension Q4 2025 561
20565N Rochestown Community Special School Cork City Special Education Extension Q3 2025 47
62050O Árdscoil Uí Urmoltaigh Bandon Post Primary Extension Q4 2025 429
62200H Coláiste Muire Crosshaven Post Primary Extension Q2 2025 518