Written answers
Tuesday, 21 October 2025
Department of Public Expenditure and Reform
An Garda Síochána
Brian Stanley (Laois, Independent)
Link to this: Individually | In context
329. To ask the Minister for Public Expenditure and Reform the budget allocation and full contract cost for construction works and refurbishment of Portlaoise Garda Station; and if he will make a statement on the matter. [56513/25]
Kevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context
Construction works at the Portlaoise Divisional Garda Headquarters are progressing on site.
The scope of the project comprises several elements; the refurbishment and multi-storey extension of an existing building, the construction of a substantial new building and all of the associated preparatory works and site completion works.
The budget allocation includes the cost of the construction works as contracted and all other development costs, as such it is not possible to publish this material until such time as the contract has been concluded.
No comments