Written answers
Tuesday, 30 September 2025
Department of Transport, Tourism and Sport
Road Projects
Ken O'Flynn (Cork North-Central, Independent Ireland Party)
Link to this: Individually | In context
240. To ask the Minister for Transport, Tourism and Sport the expected timeline for completion of the N/M20 Cork-Limerick motorway project; the projected total cost; and the extent of EU funding secured to date. [51153/25]
Darragh O'Brien (Dublin Fingal East, Fianna Fail)
Link to this: Individually | In context
As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you on the status of this project.
I can confirm that €4.5 million has been allocated for the N/M20 Cork-Limerick motorway project in 2025. As with all national roads projects in the NDP, the delivery programme for the project will be kept under review for 2026 and considered in terms of the overall funding envelope available to TII.
Noting the above position, I have referred your question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.
Ken O'Flynn (Cork North-Central, Independent Ireland Party)
Link to this: Individually | In context
241. To ask the Minister for Transport, Tourism and Sport the timeline for delivery of the Dunkettle interchange completion and the North Ring road; and if funding has been ringfenced in 2025. [51167/25]
Darragh O'Brien (Dublin Fingal East, Fianna Fail)
Link to this: Individually | In context
As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals.
Noting the above position, I have referred the question to TII for a direct reply updating you as to the latest status of the Cork City Northern Transport Project (formally the Cork Northern Ring Road), and any developments in relation to the upgraded Dunkettle Interchange (which opened in February 2024). Please advise my private office if you do not receive a reply within 10 working days.