Department of Public Expenditure and Reform

An Garda Síochána

Photo of Rose Conway-WalshRose Conway-Walsh (Mayo, Sinn Fein)
Link to this: Individually | In context

237. To ask the Minister for Public Expenditure and Reform the nature of refurbishment works that the OPW carried out at Garda stations within Mayo/Roscommon and Longford Garda division where the costs are in excess of €50,000 in 2024 and to-date in 2025; if any of the works are still ongoing at present; when these works will be completed, in tabular form; and if he will make a statement on the matter. [50314/25]

Photo of Kevin MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context

The Office of Public Works (OPW) can confirm that refurbishment works, valued in excess of €50,000 were carried out, in Garda Stations within the Mayo, Roscommon and Longford Divisions.

These Garda Stations and the nature of the works that were completed in 2024 and 2025 are outlined in the table below:

Location Nature of Works Year of Completion Status
Castlebar Upgrade of Locker Room 2024 Complete
Belmullet Universal Access Improvements 2025 Complete
Claremorris Prisoner Processing Unit Upgrade 2026 In defects liability stage
Crossmolina Universal Access Improvements 2025 Complete
Ballina Prisoner Processing Unit Upgrade 2025 Complete
Ballygar Universal Access Improvements and Window Upgrades 2025 In defects liability stage
Achill Sound Universal Access Improvements 2026 In defects liability stage
As at 22nd September 2025, there are no on-site refurbishment projects at Garda Stations in the Mayo, Roscommon or Longford divisions.