1344. To ask the Minister for Health to list all of the handover dates for the new children’s hospital, in chronological order, from the original target date, in tabular form. [49003/25]
Jennifer Carroll MacNeill (Dún Laoghaire, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The timely completion of the National Children’s Hospital Ireland (NCHI) is a Government priority. Everything possible is being done to ensure this world-class hospital will open as quickly as possible, on behalf of children, young people, and their families.
At the St. James’s campus site, work towards substantial completion of the hospital is in its final stages. The National Paediatric Hospital Development Board (NPHDB) is focused on ensuring all rooms and spaces within the hospital are completed to the standard set out in the Contract and befitting a world class healthcare facility. In addition, the technical commissioning of the hospital’s mechanical and electrical systems is underway and will continue until substantial completion.
Ultimately, substantial completion is informed by the main contractor BAM’s programme of works and its delivery against that programme. On 28 August, BAM submitted an updated programme of works. The Employer’s Representative-(ER) the independent third party responsible for administering the contract - is now reviewing this programme update for contractual compliance. It is for BAM to commit to a date when it will complete the building to the contractual standards.
The NPHDB has and continues to apply all possible contractual levers available to it to ensure substantial completion can be achieved with minimal further delays.
The table below sets out BAM’s movement of its substantial completion dates, as advised by the NPHDB
The original contractual completion date was August 2022, but mechanisms within the public works contract allow for extensions of time to be granted for legitimate delays suffered by the contractor. The current contractual completion date after agreed extensions of time are incorporated is November 2022.
Timeline of programme delays from August 2022*
BAM Baseline Programme & Monthly Progress Updates against Programme | BAM forecast Substantial Completion date | Programme Delay from original contractual completion date of August 2022* *NB contractual completion date has been adjusted to November 2022 |
---|---|---|
January 2019 – GMP Programme (ER Compliant) | August 2022 | |
March 2020 | February 2023 | 6 months |
February 2021 – Amended GMP Programme (ER Compliant) | December 2023 | 16 months (+10 months on previous update) |
May 2021 | January 2024 | 17 months (+1 month on previous update) |
January 2022 (Baseline – ER Non-compliant) | January 2024 | 17 months |
July 2022 | February 2024 | 18 months (+1 month on previous update) |
August 2022 | March 2024 | 19 months (+1 month on previous update) |
January 2023 (Baseline– ER Non- Compliant) | April 2024 | 20 months (+1 month on previous update) |
February 2023 | May 2024 | 21 months (+1 month on previous update) |
July/September 2023 (Baseline– ER Non- Compliant) | October 2024 | 26 months (+5 months on previous update) |
January 2024 | December 2024 | 28 months (+2 months on previous update) |
March 2024 | January 2025 | 29 months (+1 month on previous update) |
April 2024 | February 2025 | 30 Months (+1 month on previous update) |
September 2024 | June 2025 | 34 Months (+4 months on previous update) |
May 2025 | September 2025 | 37 Months (+2 months on previous update) |