Written answers
Wednesday, 17 September 2025
Department of Housing, Planning, and Local Government
Urban Development
Naoise Ó Muirí (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source
702. To ask the Minister for Housing, Planning, and Local Government to provide an update on the Castlebar historic core reactivation initiative project and the Castlebar military barracks project in County Mayo; and if he will make a statement on the matter. [48917/25]
Naoise Ó Muirí (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source
703. To ask the Minister for Housing, Planning, and Local Government if the Castlebar historic core reactivation initiative project and the Castlebar military barracks project have moved beyond the detailed project briefs and procurement strategies stage; the current stage of these projects; and if he will make a statement on the matter. [48918/25]
Naoise Ó Muirí (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source
704. To ask the Minister for Housing, Planning, and Local Government to provide a detailed timeline for the completion of the Castlebar historic core reactivation initiative project and the Castlebar military barracks project; specifically, when the construction tender stage is expected to commence for these projects; the estimated completion date; and if he will make a statement on the matter. [48919/25]
Naoise Ó Muirí (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source
705. To ask the Minister for Housing, Planning, and Local Government to provide an update on the sub-projects within the Castlebar historic core reactivation initiative project, particularly the old post office sub-project; the status of this subproject; the way it fits within the overall timeline of the historic core project; and if he will make a statement on the matter. [48920/25]
James Browne (Wexford, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
I propose to take Questions Nos. 702, 703, 704 and 705 together.
In 2021, following the second call for proposals under the Urban Regeneration and Development Fund (URDF), a provisional allocation of €11,027,500 in URDF support was announced for Mayo County Council's two successful proposals – the Castlebar Historic Core Reactivation Initiative (€8,527,500) and works to Castlebar Military Barracks (€2,500,000).
This followed Mayo County Council's successful application for €141,391 in URDF support towards technical assistance for the advancement of the Castlebar Military Barracks proposal under the URDF's first call for proposals in 2018.
It is a condition of URDF support that advancement of proposals/projects and related funding arrangements must accord with the Department’s Guidance on applying the Infrastructure Guidelines (formerly the Public Spending Code) to URDF-supported projects. This requires each local authority to ensure that at each of three Approval Gates it provides a submission to my Department for approval prior to progressing to the next stage of the project lifecycle. These Approval Gates are:
- AG1 - Approval in Principle (Preliminary Business Case).
- AG2 - Pre Tender Approval (Project Design, Planning and Procurement Strategy).
- AG3 - Post Tender Approval (Final Business Case).
In relation to the URDF-supported projects in Castlebar, Mayo County Council’s successful Castlebar Historic Core Reactivation Initiative proposal is made up of six individual projects, the current status of which are outlined in the following table:
Project Title | Description of Works | Project Type | Status |
---|---|---|---|
The Mall Innovation Hub (The Imperial Hotel/Daly's Hotel) | Repurpose the former Daly’s (Imperial) Hotel as an Innovation Hub. | Capital Works | AG1 – Approval in Principle issued. Design team to be appointed September 2025 |
Public Realm Works | Public Realm Works in the Mall to refurbish and rejuvenate its setting | Capital Works | AG1 – Approval in Principle issued. Design team to be appointed September 2025 |
Youth Resource Centre (The Old Post Office) | Repurpose the former Castlebar Post Office as a Community Youth Resource Centre | Capital Works | Commenced / Onsite. Construction commenced Nov 2024 |
Strategic Acquisition of properties | Purchase of 4 vacant properties at the corner of Rock Square. | Strategic Acquisition(s) | Withdrawn. Being progressed under the Council’s Call 3 Programme of Acquisitions. |
Master Plan for Ellison Street and Back Lands | Masterplan and strategic site assembly at key locations in Castlebar | Technical Assistance and Strategic Acquisition(s) | AG1 – Approval in Principle issued. Design team appointed October 2024 |
Ellison Street Infrastructure | New Links and Access routes with possible compulsory purchase | Capital Works and Strategic Acquisition(s) | AG1 – Approval in Principle issued. Design team appointed October 2024 |
The remaining projects are being progressed in parallel and are currently expected to be completed before 2028 subject, inter alia, to the timely receipt of the relevant submissions and satisfactory completion of all the remaining Approval Gates.
Regarding the successful Castlebar Military Barracks proposal, this contains the following two individual projects, the status of which are outlined in the following table:
Project Title | Description of Works | Project Type | Status |
---|---|---|---|
Detailed Design and Planning for the Barracks Site | Production of a Final Scheme Design, including Archaeological works, the Protection of Wildlife and Part 8 Planning for the detailed scheme. | Technical Assistance | AG1 – Approval in Principle issued |
Essential Enabling works to existing buildings | Works to reverse emergent dereliction in the existing buildings and to integrate the site with the historic core reactivation initiative. | Capital Works | AG1 – Approval in Principle issued |
Having received preliminary business case approval (AG1), Mayo County Council has recently tendered for an Architect-Led Integrated Design Team of Consultants to deliver a detailed design and secure planning consent for the Barracks site. The tender process for this appointment is expected to conclude in the coming weeks.
In relation to the enabling works element of the proposal, the estimated costs associated with these works are currently less than €20m. Therefore, and subject to the costs and scope of works remaining as approved in their AG1 submission, the Council is also approved to proceed with finalising the detailed design and procurement process for the Enabling Works element of the proposal. The outcome of this element must also be submitted to my Department as part of that project's AG3 submission.
Subject to satisfactory completion of these steps, these projects may be in a position to be completed by Q2 2027.
Finally, while my Department works closely and communicates regularly with Mayo County Council in respect of project funding, responsibility for the advancement of these URDF-supported projects through the various stages of the project lifecycle is, in the first instance, a matter for the Sponsoring Agency (in this case Mayo County Council). Any further queries regarding timelines for these projects can be directed to the Council.
No comments