Monday, 8 September 2025
Department of Education and Skills
Departmental Expenditure
Cormac Devlin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context
2741. To ask the Minister for Education and Skills for an update on the Ulster University Derry campus expansion supported under the Shared Island Fund, including scope, capital profile, co-funders and delivery timeline; and if he will make a statement on the matter. [47401/25]
James Lawless (Kildare North, Fianna Fail)
Link to this: Individually | In context
In 2023, the Government approved funding of up to 85% (£38.25m) for the construction cost of a new Teaching Building on the Derry campus through an allocation of up to €44.5m from the Shared Island Fund. Ulster University (UU) has committed to funding the 15% balance (£12.75m) as well as any cost overruns. UU estimates a 48 to 60-month construction period.
Following extensive pre-planning engagement with Derry-Strabane District Council, a full planning application was submitted in June 2025. Subject to approval, UU hope to have the facility ready for students in the 2028/ 29 academic year.
Officials in my Department will continue to work closely UU senior management as this project progresses.