225. To ask the Taoiseach and Minister for Defence when the runway at casement aerodrome was last resurfaced; when the runway is next scheduled to be resurfaced. [46713/25]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context

A contract for Runway and Taxiway Overlay works was completed in December 2002 and a subsequent contract for Apron Repairs work was completed in November 2005. Ongoing surface maintenance is provided as required and the most recent repairs were undertaken in 2021 and 2022. I am advised by the military authorities that there are no plans to have the runways at Casement Aerodrome, Baldonnel resurfaced this year.