610. To ask the Minister for Public Expenditure and Reform the full cost to date associated with a project (details supplied); a breakdown of the costs and suppliers; the overall initial cost; the cost to date in 2025; any additional costs and overspends from original costings; the projected total finished cost; a timeline for opening; and if he will make a statement on the matter. [44677/25]

Photo of Kevin MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context

The information requested is being compiled and the OPW will respond directly to the Deputy.

Photo of Peadar TóibínPeadar Tóibín (Meath West, Aontú)
Link to this: Individually | In context

611. To ask the Minister for Public Expenditure and Reform for an update on works to a project (details supplied); if he is aware of any report submitted regarding the current levels of dry rot in the building; and if he will make a statement on the matter. [44678/25]

Photo of Kevin MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context

The project for a new Garda Station at Bailieborough, Co. Cavan includes conservation of the existing former National Irish Bank (NIB) building and the construction of a new three storey over basement building to the rear on a site located on the town’s main street.  A significant portion of these works are now complete.

The purchase of a neighbouring property by the Office of Public Works (OPW) allowed for the provision of extra secure parking spaces and safer processing of those being arrested.  Plans to facilitate this were approved by Garda Estate Management and the associated Planning Permission for the works was granted in September 2023.  These works are progressing as part of the overall project.

Dry Rot in the original NIB Building is being continuously monitored.  Final remedial works to the areas impacted by dry rot are underway in advance of completion of the works.