Department of Education and Skills

Schools Building Projects

Photo of Cathal CroweCathal Crowe (Clare, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

1156. To ask the Minister for Education and Skills the number of school building projects that have been completed, by county, in tabular form since 2020; the funding allocated for same, by county since 2020; to provide a breakdown the total number of projects currently under construction, per county; to provide a breakdown of the total number of projects currently in planning and design, per county; and if she will make a statement on the matter. [42725/25]

Photo of Helen McEnteeHelen McEntee (Meath East, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Since 2020, my department has invested over €6 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,400 school building projects. Government support for this investment, including by way of supplementary capital funding, has delivered real benefits for school communities.??

My department's school building projects are being delivered to ambitious timeframes, and the position on individual projects evolves all the time as they advance through various stages.? The status of all projects is set out at (www.gov.ie). This is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction.??

Please see below table which outlines Capital expenditure 2020 to date, projects completed 2020 to date, projects in construction and in the pipeline.

Department Capital Expenditure 2020 to date €m School Building Projects Completed 2020-to date School Building Projects in Construction (LS/ASA/Modular) School Building Projects at advanced stages of design & planning (LS/ASA/Modular)
Carlow 45.79 22 9 8
Cavan 81.41 28 7 11
Clare 130.46 24 11 17
Cork 714.92 158 48 57
Donegal 197.57 62 19 21
Dublin 1508.94 304 75 99
Galway 217.72 84 23 27
Kerry 136.38 60 24 23
Kildare 355.37 54 22 21
Kilkenny 179.27 46 13 15
Laois 118.45 31 13 11
Leitrim 23.07 8 3 5
Limerick 269.14 52 10 28
Longford 40.51 13 4 5
Louth 106.91 26 16 9
Mayo 139.69 58 12 21
Meath 408.64 64 26 29
Monaghan 87.39 27 8 13
Offaly 78.8 30 4 11
Roscommon 56.25 28 5 11
Sligo 61.72 21 5 10
Tipperary 160.23 71 14 18
Waterford 128.87 28 16 12
Westmeath 150.37 27 6 15
Wexford 159.96 64 23 16
Wicklow 209.11 46 19 22

My Department also completed more than 3,000 smaller-scale school building improvements through emergency works and summer works schemes during this timeframe.