218. To ask the Minister for Public Expenditure and Reform to provide a list of all capital upgrades to Baltinglass Garda station since 2005. [35112/25]

Photo of Kevin MoranKevin Moran (Longford-Westmeath, Independent)
Link to this: Individually | In context

An non-exhaustive list of capital upgrades to Baltinglass Garda station since 2018 is summarised in Table A below.

The information provided reflects what has been reasonably accessibly within the PQ response timeframe, it does not include paper-based information that has been archived.

Table A.

Description
Cell Upgrade
Conversion of Garage to Locker Room
Security upgrade works
Lights in canteen and office
Installation of Power and data
Preventative Maintenance
Power and data for conversion of female changing room & Traffic Office
Installation of AC in Comms Room
Installation of Data Points to facilitate migration to VOIP Telephony
Installation of Data Ports
Installation of Power and Power Distribution Unit
Installation of a Burco Boiler
There are a number of capital upgrades to Baltinglass Garda station being progressed.

Details of these projects are summarized below in Table B.

Description Comment
Kitchen and Bathroom Upgrade, Parking and Accessibility Currently at Tender preparation stage, anticipate contract award before the end of 2025.
New Proposed kitchen at Baltinglass To progress after current Universal Access project above.