Written answers
Thursday, 29 May 2025
Department of Public Expenditure and Reform
Capital Expenditure Programme
Tony McCormack (Offaly, Fianna Fail)
Link to this: Individually | In context
121. To ask the Minister for Public Expenditure and Reform if total capital investment to date in 2025 is on profile; and if he will make a statement on the matter. [27987/25]
Jack Chambers (Dublin West, Fianna Fail)
Link to this: Individually | In context
Public expenditure management and achieving value for money, within agreed ceilings voted by Dáil Éireann, is a key responsibility of every Department and Minister.
Expenditure profiles for 2025 were completed by all Votes in February and performance against these profiles is used throughout the year to monitor expenditure trends, with the details published monthly in the Fiscal Monitor.
The latest figures up to end-April show that gross capital expenditure of €3,575 million is within profile of €3,765 million and accounts for just over 24% of the overall 2025 REV capital allocation of €14,841 million.
While the majority of Vote Groups remain at or near profile, my Department will continue to communicate and engage with Departments to ensure expenditure is managed within the overall fiscal parameters.
Barry Heneghan (Dublin Bay North, Independent)
Link to this: Individually | In context
122. To ask the Minister for Public Expenditure and Reform if he will confirm the capital allocations made in 2024 to public infrastructure projects located in Dublin Bay North, including schools, transport, and healthcare facilities; and if he will make a statement on the matter. [28249/25]
Jack Chambers (Dublin West, Fianna Fail)
Link to this: Individually | In context
As Minister for Public Expenditure, NDP Delivery and Reform I am responsible for setting the overall capital allocations across Departments and for monitoring monthly expenditure at Departmental level. The responsibility for the management and delivery of individual investment projects or sectoral policy strategies, within the allocations agreed under the National Development Plan (NDP), rests with the individual sponsoring Department in each case. Each Minister is responsible for deciding on the priority programmes and projects that will be delivered under their remit within the NDP and for setting out the timelines for delivery. Expenditure is therefore allocated and monitored on a Departmental basis and not a geographical basis.
The Government committed €165 billion towards capital investment through the National Development Plan (NDP) 2021-30 published in 2021. An additional €2.25 billion of windfall corporate tax receipts has also been allocated from 2024 to 2026, to provide funding for critical infrastructure projects that are at an advanced stage, as well as to the existing Climate Action Fund. This builds on the existing funding already available under the NDP out to 2026 and it will mean more schools, housing, transport and healthcare projects can be progressed and delivered for our people across all regions.
In 2025, €15 billion is being made available from the Exchequer for investment in public capital projects. This level of expenditure will be pivotal in consolidating the progress already made, supporting balanced regional development and, most importantly, delivering the necessary infrastructure to support our future climate change obligations as well as our social and economic requirements.
The Government is detailing the delivery of the NDP at regular intervals to inform the public on the implementation of Project Ireland 2040. This is achieved through regular updates of the Project Ireland 2040 capital investment tracker and map, the latest versions of which will be published shortly.
The capital investment tracker provides a composite update on the progress of all major investments with an estimated cost of greater than €20 million. Accompanying the tracker, the myProjectIreland interactive map details projects across the country and provides details on specific projects by county, and contains smaller investments such as schools, healthcare facilities and social housing projects. Search facilities also allow citizens to view projects in their regional area, by city, by county or by eircode.
No comments