Written answers
Tuesday, 13 May 2025
Department of An Taoiseach
Departmental Projects
Cathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context
247. To ask the Taoiseach the number of IT projects within his Department, or bodies under its aegis, which have been allocated funds in excess of €1 million in the years 2020 to date; the purpose of any projects; the initial estimate to complete for such projects; the total amount expended to date; the total estimated cost to complete; the estimated timeframe by which they expected to be completed; by project; by year; in tabular form. [22950/25]
Micheál Martin (Cork South-Central, Fianna Fail)
Link to this: Individually | In context
Neither the Department of the Taoiseach nor the National Economic and Social Development Office - the only body under the aegis of the Department of the Taoiseach - have allocated funds in excess of €1 million to any IT projects in the specified time period.
No comments