286. To ask the Minister for Transport, Tourism and Sport if he will provide a schedule of all capital projects being delivered or which have been completed by his Department and organisations under the aegis of his Department since 1 January 2020; the total project cost of projects in excess of €500,000, or of any other capital projects below this that have come to his Department's attention for reasons of overspend or due to the fact that they failed to be delivered; and if he will make a statement on the matter. [16693/25]
Darragh O'Brien (Dublin Fingal East, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
In the main, Capital projects & investments are delivered by the relevant agencies under the remit of my Department.
I have referred this question to the agencies under my remit for further reply. If the Deputy has not received a reply within ten working days please contact my private office.
In relation to departmental projects exceeding 500k, please see table below:
Year | Capital Project | Cost (over 500k) |
---|---|---|
2022 | Refurbishment and fit out of basement in Georgian Block | €668,662.34 |
2023 | Re-development of Front Entrance and Plaza | €595,951.54 |
Year | Project | Cost |
---|---|---|
2018-2022 | Summercove IRCG Station | €536,000 |
2024 | Bonmahon IRCG Station | €5,040,000 |
2024 to date | Westport IRCG Station | €1,200,000 |