Written answers
Tuesday, 8 April 2025
Department of Employment Affairs and Social Protection
Departmental Data
Aidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source
665. To ask the Minister for Employment Affairs and Social Protection if he will provide a schedule of all capital projects being delivered or which have been completed by his Department and organisations under the aegis of his Department since 1 January 2020; the total project cost of projects in excess of €500,000, or of any other capital projects below this that have come to his Department's attention for reasons of overspend or due to the fact that they failed to be delivered; and if he will make a statement on the matter. [16691/25]
Dara Calleary (Mayo, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
Capital building projects for the Department of Social Protection are delivered by the Office of Public Works (OPW). The OPW is responsible for the design, procurement, and delivery of these projects, ensuring they meet the necessary standards, requirements and value for money. My Department funds some of these OPW capital projects from its own capital budget.
My Department funded the OPW capital projects listed below which were completed between 2020 and March 2025.
Capital Building Projects 2020- March 2025 | |
---|---|
Tuam OId Library Project | |
Fitout Fermoy | |
Tallaght Intreo Fitout | |
Fit Out Mallow | |
Sligo Pension Office 1st Floor Retrofit & Refurbishment | |
LED Light Upgrade, Dundalk Government Buildings | |
Kilbarrack Refurbishment | |
Dungarvan Fitout | |
Lifford Fitout | |
LED Upgrade, Finglas Intreo | |
Theatre Court, Limerick Fitout | |
LED upgrade, Ballyfermot Intreo | |
Fire Suppression System, Goldsmith House | |
Pery Court, Limerick Fitout |
The below table depicts the capital building projects that were completed between 2020 and March 2025 that were in excess of €500,000.
Capital Building Projects in excess of €500,000 | Cost (€) |
---|---|
Tuam OId Library Project | 1,493,375 |
Fitout Fermoy | 1,178,484 |
Tallaght Intreo Fitout | 1,022,632 |
Fit Out Mallow | 791,417 |
As regards the organisations under the aegis of my Department, the following table outlines capital works carried out since 2020.
Capital Building Projects 2020- March 2025 | |
---|---|
Citizens Information Board (CIB) - Refurbishment of leasehold premises at 4 The Parade, Kilkenny |
My Department has not had any overspends in the delivery of capital building works. However, there was an overspend of €4,267 on the CIB refurbishment costs, which were approximately €287,000 in total.