Schools Building Projects

Photo of Emer CurrieEmer Currie (Dublin West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

567. To ask the Minister for Education and Skills when the next Stage 2a meeting (details supplied) will be held, following a previous meeting in October 2024; and if she will make a statement on the matter. [10796/25]

Photo of Helen McEnteeHelen McEntee (Meath East, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The current position in respect of the joint major building project referred to by the Deputy is as follows;

The major project for St. John Bosco Boys JNS, St. John Bosco SNS, and Mary Help of Christians GNS is currently at Stage 2(a) of Architectural Planning - Developed Design - which is a crucial element of the architectural planning process as it is at this stage that the design is developed to a stage where it can be fully cost planned and prepared to lodge for statutory approvals.

Following the Stage 2(a) Stakeholders meeting which took place on Wednesday 16th October, the Design Team have been addressing the Department comments.

The Design Team submitted a revised Stage 2(a) Report to my Department on 1st March 2025.

An initial review of the revised report will be carried out by Department officials in due course. Until this review is complete, it is not possible to provide a date for the rescheduled Stage 2(a) Stakeholders meeting.

The Department is committed to progressing this project through architectural planning and supporting the design team in preparing the project design so that it can apply for all statutory approvals, including planning permission.