Written answers
Thursday, 20 February 2025
Department of Communications, Climate Action and Environment
Electricity Grid
Brendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
112. To ask the Minister for Communications, Climate Action and Environment the proposed investment in the electricity grid; if there are specific proposals to update the grid particularly in rural areas; and if he will make a statement on the matter. [6804/25]
Darragh O'Brien (Dublin Fingal East, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
Issues regarding the development of the national electricity grid rest with EirGrid, as Transmission System Operator, and ESB Networks, as Distribution System Operator, who are independent of me as Minister in the exercise of their respective functions. Both entities are overseen by the independent regulator, the Commission for Regulation of Utilities (CRU).
The Government does not have any role in the delivery of electricity infrastructure on the ground. This is consistent with the 2012 Government Policy Statement on the Strategic Importance of Transmission and Other Energy Infrastructure which states: ‘The Government does not seek to direct EirGrid and ESB Networks or other energy infrastructure developers to particular sites or routes or technologies’.
Planning, building, safely operating and maintaining the electricity system are functions which are assigned to the respective Distribution and Transmission System Operators and for which they are accountable to the CRU. It is for system operators to determine the means of delivery of infrastructure.
Notwithstanding the above, I met with representatives from the CRU and ESB Networks on the 31 January to discuss the Storm Éowyn response and the impact on customers. I have requested that a number of actions be taken including an enhanced Winter 2025 Grid Resilience Plan. This will be developed and will be implemented by ESB Networks between March and October to enhance the resilience of the grid in the most vulnerable locations for the upcoming winter.
I have also requested a full review by ESB Networks and CRU, as part of the PR6 (Sixth Annual Price Review) decision-making process, of the planned grid enhancement having regard to the damage caused by Storm Éowyn, with specific additional projects and investments identified to future proof Ireland’s energy grid and to adapt to the challenges of climate change.