Schools Building Projects

Photo of Eamon ScanlonEamon Scanlon (Sligo-Leitrim, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

451. To ask the Minister for Education and Skills the status of the development of a new school application (details supplied); and if she will make a statement on the matter. [2729/25]

Photo of Helen McEnteeHelen McEntee (Meath East, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy will be delivered under my Department's ADAPT Programme.

The ADAPT Programme uses a professional external Programme Manager to co-ordinate and drive the Design Team to achieve the best possible timeframe for the project through the design stages of architectural planning to Tender and Construction.

The brief for this project is the development of a new 12 Classroom primary school with additional classrooms for pupils with Special Education needs, on a green-field site.

Following receipt and review of the Stage 1 Addendum during May 2024, the major building project was approved to progress to Stage 2(a) of Architectural Planning – Developed Design, where the preferred agreed design option can be developed to a stage where the project is fully cost planned and the scheme can be prepared to lodge for statutory approvals with the local authority.

On receipt and review of the Stage 2(a) Submission from the Design Team, the Stage 2(a) Stakeholders meeting can then be arranged. Following that meeting, the school authorities and design team will be advised regarding project progression.