Written answers
Tuesday, 22 October 2024
Department of Transport, Tourism and Sport
Road Projects
Pádraig O'Sullivan (Cork North Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
163. To ask the Minister for Transport, Tourism and Sport what further progress has been made on the Mallow relief road; and if he will make a statement on the matter. [42378/24]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you on the status of this project.
I can confirm that €300,000 was initially allocated for the Mallow Relief Road project in 2024. This was subsequently increased to €800,000 to enable the completion of the environmental impact assessment report. As with all national roads projects in the NDP, the delivery programme for the project will be kept under review for 2025 and considered in terms of the overall funding envelope available to TII.
Noting the above position, I have referred your question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.
Pádraig O'Sullivan (Cork North Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
164. To ask the Minister for Transport, Tourism and Sport for an update on the M20 Cork-Limerick motorway; and if he will make a statement on the matter. [42379/24]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you on the status of this project.
I can confirm that €4,040,000 has been allocated for the M20 Cork to Limerick project in 2024. As with all national roads projects in the NDP, the delivery programme for the project will be kept under review for 2025 and considered in terms of the overall funding envelope available to TII.
Noting the above position, I have referred your question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.
No comments