Written answers

Thursday, 17 October 2024

Department of Transport, Tourism and Sport

Road Projects

Photo of Robert TroyRobert Troy (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

58. To ask the Minister for Transport, Tourism and Sport for an update on the N4 Mullingar to Rooskey upgrade; and if he will make a statement on the matter. [42008/24]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

I thank the Deputy for his question. I know that this project is of great interest to him.

The Government has earmarked €5.1bn for capital spending on new national roads projects from 2021 to 2030 as part of the NDP. As the greater portion of this funding becomes available in the second half of the decade, this meant that there was a constraint on the funding available for new projects this year.

Approximately €411m of exchequer capital funds have been provided for national roads through TII to local authorities in 2024. These allocations were announced by the Department of Transport and TII on the 22nd of February 2024.

Having regard to the funding constraint outlined above, it was not possible to provide an allocation to all new national road projects in the NDP for 2024. However, the majority of projects have been allocated funding, including the N4 Mullingar to Longford Scheme, which has received an allocation of €1.44 million.

This project, as proposed, would run for 54km between Mullingar and Rooskey, bypassing towns and villages including Rathowen, Edgeworthstown and Newtown Forbes. A public consultation announcing an Emerging Preferred Transport Corridor was held in July and work is ongoing on finalising the preferred route. It is expected that the route selection phase will conclude before the end of the year. The next phase of the project would involve the detailed design and environmental evaluation of the project in order to complete a preliminary business case.

As with all national roads projects included in the NDP, the delivery programme for the N4 project will be kept under review this year and in future years. This will include consideration of all developments in relation to the project.

I hope that this information is of assistance.

Comments

No comments

Log in or join to post a public comment.