Written answers
Thursday, 26 September 2024
Department of Education and Skills
Schools Building Projects
Jennifer Whitmore (Wicklow, Social Democrats)
Link to this: Individually | In context | Oireachtas source
151. To ask the Minister for Education and Skills when construction work will commence for a school (details supplied); the timeline for delivery and completion of this project; and if she will make a statement on the matter. [38261/24]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
The project to which the Deputy refers is devolved for delivery to Kildare and Wicklow Education and Training Board (KWETB).
The project is currently at Stage 2b of the architectural process. The planning application was lodged with Wicklow County Council and full grant of planning permission was received in Q2 2024.
When Stage 2b has been finalised and approved, the next stage is tendering for a contractor and then onwards to construction in due course.
While at this early stage it is not possible to provide a timeline for the next and subsequent project stages, the NDFA will be engaging directly with the school authorities to keep them informed of progress.
Jennifer Whitmore (Wicklow, Social Democrats)
Link to this: Individually | In context | Oireachtas source
152. To ask the Minister for Education and Skills when construction work will commence for a school (details supplied); the timeline for delivery and completion of this project; and if she will make a statement on the matter. [38262/24]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
The project to which the Deputy refers has been devolved to the National Development Finance Agency (NDFA) for delivery as part of a programme of school building projects.
The project is currently at Stage 2b of the architectural process. The planning application was lodged with Wicklow County Council and full grant of planning permission has been received.
When Stage 2b has been finalised and approved, the next stage is tendering for a contractor and then onwards to construction in due course.
While at this early stage it is not possible to provide a timeline for the next and subsequent project stages, the NDFA will be engaging directly with the school authorities to keep them informed of progress.
Jennifer Whitmore (Wicklow, Social Democrats)
Link to this: Individually | In context | Oireachtas source
153. To ask the Minister for Education and Skills when construction work will commence for a school (details supplied); the timeline for delivery and completion of this project; and if she will make a statement on the matter. [38263/24]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
The project to which the Deputy refers has been devolved to the National Development Finance Agency (NDFA) for delivery as part of a programme of school building projects.
The project is currently at Stage 2b of the architectural process. A planning application was lodged with Wicklow County Council and planning permission was granted in Quarter 1 2024.
When Stage 2b has been finalised and approved, the next stage is tendering for a contractor and then onwards to construction in due course.
While at this early stage it is not possible to provide a timeline for the next and subsequent project stages, the NDFA will be engaging directly with the school authorities to keep them informed of progress.
No comments