Written answers

Tuesday, 21 May 2024

Department of Public Expenditure and Reform

Data Centres

Photo of Catherine MurphyCatherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

241. To ask the Minister for Public Expenditure and Reform the amount the OPW has spent to date on the construction of a new public sector data centre; and when this centre will open. [22379/24]

Photo of Kieran O'DonnellKieran O'Donnell (Limerick City, Fine Gael)
Link to this: Individually | In context | Oireachtas source

To date €28,323,757.06 has been spent on the construction of the new Public Sector Data Centre,

This Figure is inclusive of VAT. Substantial completion is scheduled for May 2025.