162. To ask the Minister for Transport, Tourism and Sport if he has assessed the recent submission from Kilkenny County Council dated 19 April 2024 in response to the SRAD queries relative to the next phase of the Kilkenny ring road extension; if he will provide the appropriate level of funding to allow the project to proceed to the next stage; and if he will make a statement on the matter. [21241/24]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
In accordance with the provisions of Section 13 of the Roads Act 1993, each local authority has statutory responsibility for the improvement and maintenance of their regional and local roads. Works on those roads are funded from local authorities' own resources and are supplemented by State Road grants. Of these grants, the vast majority (approximately 90%) are targeted at the maintenance and renewal of the network with c. 10% of the remaining funding invested in new roads/bridges or for road realignments.
Any new road projects that seek State funding are assessed by the Department on a case-by-case basis. All projects proposed by local authorities for consideration must comply with the requirements of the Infrastructure Guidelines (formerly the Public Spending Code) and the Department's Transport Appraisal Framework. Given the limited funding available for regional and local road improvement works it is important for local authorities to prioritise projects within their overall area of responsibility with these requirements in mind.
In line with Government requirements Kilkenny County Council produced a Strategic Assessment Report (SAR) for the Kilkenny Northern Ring Road Extension and a draft was forwarded to the Department in January 2023. The Department reviewed the SAR and returned its comments and observations to Kilkenny County Council for consideration.
Since then, both the Public Spending Code and the Department’s Transport Appraisal Framework (TAF) guidance have been updated - the Department continues to liaise with the Council regarding new requirements under the new infrastructure Guidelines and the TAF including the preparation of a Project Outline Document (POD) and business case incorporating the work already undertaken at the SAR stage.
The Department has recently received an updated POD which is currently under review by the Department’s Strategic Research and Analysis Division and Regional and Local Roads Division. Following this review, the Department will further engage with Kilkenny County Council on the Kilkenny Northern Ring Road Project. While this process is underway funding has been allocated for Traffic/Junction Analysis in the Butts Green area of the City to further assess and understand traffic patterns in the city.
John McGuinness (Carlow-Kilkenny, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
163. To ask the Minister for Transport, Tourism and Sport if the required amount of funding will be allocated immediately to allow a continuation of the N24 road project; and if he will make a statement on the matter. [21242/24]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you.
I can confirm that €650,000 was allocated for the N24 Cahir to Limerick Junction scheme in 2024. While it was not possible to provide an allocation to the N24 Waterford to Cahir scheme, as with all national roads projects in the NDP, the delivery programme for this project will be kept under review in future years and considered in terms of the overall funding envelope available to TII.
Noting the above position, I have referred your question to TII for a direct reply updating you regarding the status of these projects. Please advise my private office if you do not receive a reply within 10 working days.