Written answers
Thursday, 2 May 2024
Department of Public Expenditure and Reform
An Garda Síochána
Catherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source
137. To ask the Minister for Public Expenditure and Reform to provide a schedule of Garda stations in Kildare and Wicklow that are subject of capital works, by location; the budget associated with same and nature of works; the stage the projects are at currently; and the expected completion date. [20084/24]
Catherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source
138. To ask the Minister for Public Expenditure and Reform to provide a schedule of Garda stations in Kildare and Wicklow that are subject of internal renovation and or retrofitting works by locations; the budget associated with same and nature of works; the stage the projects are at currently; and the expected completion date. [20085/24]
Kieran O'Donnell (Limerick City, Fine Gael)
Link to this: Individually | In context | Oireachtas source
I propose to take Questions Nos. 137 and 138 together.
The Office of Public Works can confirm that Garda stations in Kildare and Wicklow are subject of internal renovation, retrofitting and or capital works. The Garda Stations, the nature of the works and the stage the projects are at are presented in tabulated format below. As these projects are at various stages of the tender / construction process, budget estimates are considered commercially sensitive at this time. The expected completion date of the works is listed below and include works where the estimated value is in excess of €125,000 only. The projects outlined relate to works funded by both OPW and An Garda Síochána.
The commencement/completion dates for the works are subject to the final sign off, of operational and design requirements by An Garda Síochána and a successful tendering process.
Garda Station | The nature of the works | Current stage of the project | The cost of the works excluding VAT | Expected completion date. |
---|---|---|---|---|
Arklow GS | Cell Upgrade | Design Stage. | TBC | Q4 2024 |
Baltinglass GS | Universal Access Works | Tender Preparation Stage. | TBC | Q4 2024 |
Shillelagh GS | Fabric Upgrade and Refurbishment Works | On Site. | TBC | Q3 2024 |
Tinahely GS | Universal Access Works and Refurbishment Works | On Site. | TBC | Q3 2024 |
Wicklow GS | Cell Upgrade | Tender Preparation stage. | TBC | Q4 2024 |
Athy GS | Cell Upgrade | On Site. | TBC | Q2 2024 |
Bray GS | Roof Repairs and Atrium Glazing | Tender Preparation stage | TBC | Q4 2024 |