Written answers

Thursday, 14 December 2023

Department of Transport, Tourism and Sport

Local Authorities

Photo of Brendan SmithBrendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

201. To ask the Minister for Transport, Tourism and Sport if he will give further consideration to the issues raised in a motion passed by a local authority (details supplied); and if he will make a statement on the matter. [56079/23]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

The improvement and maintenance of regional and local roads is the statutory responsibility of each local authority. Exchequer funding is intended to supplement local authorities' own resources.

In February this year I was delighted to announce an Exchequer investment of €626 million in our regional and local road networks which included an increase in funding of €20 million for road pavement and rehabilitation works.

At the start of 2023 Monaghan County Council were allocated over €16.2 million for regional and local road maintenance and improvement works which was to be used in conjunction with the councils own resources. In recognition of the fact that inflation is having a significant impact on the cost of delivering annual road programmes, local authorities were notified in July of a supplementary allocation of €22.5 million for their key road strengthening programmes. Monaghan County Council was allocated an additional €579,991 under this supplementary allocation.

Monaghan County Council used the State funding to help support an extensive 2023 programme of maintenance and improvement works alongside additional projects such as the N2 to N12 Link road (Monaghan Business Park) which was funded under the Strategic Regional and Local Roads Grant Programme, as well as four projects funded using the Specific Improvement Grant Scheme (Brackly Bridge Replacement; R181 Drumillard to Crossduff; R180/R181 Junction; and L63101 Drumary Bridge Replacement). Funding has also been provided to support a pilot project that examines and monitors the performance of recycled construction materials in pavement projects.

The main regional and local road grant programmes are focussed on three specific policy objectives: surface sealing to protect against water damage; road strengthening to lengthen the life of roads; and a Discretionary Grant scheme which supports a range of activities including pothole repairs, renewal of signs/lines, and winter maintenance. These three grant programmes account for most of the available funding with allocations being based on the length of the road network within a local authority's area of responsibility with some account taken of traffic. It is envisaged that grants will continue to be made available on this basis as it is the most equitable approach.

Apart from a requirement that 15% of the road strengthening budget is spent on regional roads, the allocation of funding to different categories of road is a matter for each individual local authority, having regard to the funding available to it from local and central sources as well as their own particular priorities. Allocations for the 2024 Regional and Local Roads Grant Programmes will be made early in the new year. Funding will continue to be allocated based on the length of the road network within a local authority's area of responsibility and is intended to supplement realistic contributions from local authorities’ own resources.

Photo of Brendan SmithBrendan Smith (Cavan-Monaghan, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

202. To ask the Minister for Transport, Tourism and Sport if he will have further consideration given to the issues raised in a motion passed by a local authority (details supplied); and if he will make a statement on the matter. [56082/23]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Public Spending Code and the necessary statutory approvals.

In 2023, €600,000 was allocated for the N2 Ardee to south of Castleblayney scheme. The funding for this scheme, as with all schemes in the NDP will be kept under review and considered in terms of the overall funding envelope available to TII. Allocations for 2024 will be announced in the coming weeks.

Noting the above position, I have referred your question to TII for a direct update as to the status of this scheme. Please advise my private office if you do not receive a reply within 10 working days.

Comments

No comments

Log in or join to post a public comment.