Written answers
Tuesday, 17 October 2023
Department of Public Expenditure and Reform
Flood Risk Management
Pauline Tully (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
181. To ask the Minister for Public Expenditure and Reform the flood relief projects currently under construction and funded by the OPW; and when each of these flood relief projects will be completed, in tabular form. [45291/23]
Patrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source
The Government has committed €1.3 billion to the delivery of flood relief schemes over the lifetime of the National Development Plan to 2030 to protect approximately 23,000 properties in communities that are under threat from river and coastal flood risk. Since 2018, as part of a phased approach to scheme delivery, this funding has allowed the OPW to increase its work on flood relief schemes to over 90 schemes at design and construction at this time.
There are currently seven flood relief schemes at Construction Stage. The following table lists these schemes and their anticipated substantial completion dates.
OPW Flood Relief Scheme | Substantial Completion |
---|---|
Athlone Flood Alleviation Scheme | Q2 2024 |
Dodder Phase 2C, 2D, 2E Flood Relief Scheme | Q4 2023 |
Glashaboy (Glanmire / Sallybrook) Flood Relief Scheme | Q4 2026 |
Morell River Flood Management Scheme | Q4 2025 |
River Mall (Templemore) Flood Relief Scheme | Q2 2024 |
Springfield Flood Relief Scheme | Q2 2024 |
Whitechurch Stream Flood Alleviation Scheme | Q4 2025 |