Written answers
Monday, 11 September 2023
Department of Transport, Tourism and Sport
Capital Expenditure Programme
Rose Conway-Walsh (Mayo, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
257. To ask the Minister for Transport, Tourism and Sport the reason for capital expenditure running €212 million behind profile, as outlined in the Mid-Year Expenditure Report; and if he will make a statement on the matter. [37477/23]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
The table below sets out the expenditure compared to profile to end Q2 2023 and represents the broad picture at the end of Q2, prior to the publication of the Mid-Year Expenditure Report.
Programme | 2023 Budget (€m) | End Q2 Profile (€m) | End Q2 Outturn (€m) |
---|---|---|---|
A - Active Travel and Greenways | 356.024 | 42.806 | 41.264 |
B - Carbon Reduction and Public Transport | 1,007.720 | 408.170 | 236.719 |
C - Road Networks and Road Safety | 1,228.550 | 264.847 | 239.479 |
D - Civil Aviation | 19.774 | 0.061 | 0.052 |
E - Maritime Transport and Safety | 10.186 | 1.518 | 0.418 |
As the table demonstrates, the bulk of the underspend to end Q2 is related to delays in public transport investment. The reasons for the underspend are set out below.
- The contract award for the signalling element of the Cork Commuter Rail project was signed on 30th June, delaying payment by circa two months .
- A second milestone payment for DART+ fleet is due in Q3 to bring expenditure back on profile.
- Expected Kishoge station works deferred by a short period.
- A delay in the procurement process for the Client Partner contract for MetroLink. This contract was signed in Q2 and expenditure is expected to get back on profile.
- Delays in works for the BusConnects depot electrification programme. Work has begun in Summerhill and expenditure is expected to return to profile.
- Delays in the payments for new bus fleet.?The fleet is expected to be tested and begin entering service this year and expenditure should increase by year end.
My Department will shortly bring the Q2 capital memo to cabinet, which will provide a detailed overview of the investment progress to end Q2 2023.