713. To ask the Minister for Education and Skills to provide clarification on the anticipated completion dates for the manufacturing of the modular classrooms for a school (details supplied) and the projected and provide insights into the factors contributing to this revised projection and the contingency put in place by the NCSE for parents of students who have been enrolled at this school; and if she will make a statement on the matter. [38802/23]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
As the Deputy is aware, my Department approved funding for the provision of two special classes under the Additional School Accommodation scheme for the school in question. The project is devolved to the school authority and is being delivered under the Department’s SEN Reconfiguration and Modular Accommodation programme.
This programme provides project management supports to enable the accommodation to be provided as quickly as possible and helps to ease the administrative workload for individual schools in relation to the management and delivery of the project. The use of the Department's Modular Accommodation Framework also assists in ensuring lead in periods for procurement of modular accommodation are minimised to the greatest extent possible.
The overall construction sector environment is nevertheless challenging. The Department and the Project Management company are doing everything possible to ensure that the project is delivered as quickly as possible. My Department is fully aware of the urgency in respect of this important project and will work closely with the school authority and its project manager in order to ensure the project is completed as soon as possible and that the school is updated directly on all progress and timelines. While the manufacture of the required modular units is progressing, it is anticipated that site works will commence shortly with a target for practical completion for early November.
Alan Dillon (Mayo, Fine Gael)
Link to this: Individually | In context | Oireachtas source
714. To ask the Minister for Education and Skills to provide clarification on the anticipated completion dates for the manufacturing of the modular classrooms for a school (details supplied) and the projected and provided insights into the factors contributing to this revised projection and the contingencies put in place for students who have been enrolled at this school; and if she will make a statement on the matter. [38803/23]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
I am pleased to advise the Deputy that approval for additional bespoke modular accommodation comprising of 7 x 60m2mainstream classrooms, 5 x Special Education Tuition rooms, 1 x Art room, 1 x Science room + prep area together with the reconfiguration of an existing space to provide accommodation for a Special Educational Needs class has issued to the school in question. The Special Educational Needs classroom is due for handover to the School Authority next week.
The project is being delivered under my Department’s Devolved SEN Reconfiguration and Modular Accommodation programme. This programme provides project management supports to enable the accommodation to be provided as quickly as possible and helps to ease the administrative workload for individual schools in relation to the management and delivery of the project.
The use of my Department's Modular Accommodation Framework also assists in ensuring lead in periods for procurement of modular accommodation are minimised to the greatest extent possible.
The overall construction sector environment is challenging and my Department and the Project Management Company are doing everything possible to ensure that modular accommodation is delivered as quickly as possible. My Department is fully aware of the urgency in respect of same and will be working with the School Authority to keep it updated on overall project delivery and timelines.
The modular project, at the school in question, is progressing as per programme. The overall modular design is agreed with the necessary statutory applications expected to be lodged over the next fortnight, with the contractor expected to commence on site in late September.
The School Authority has overall responsibility for the delivery of this project.
Alan Dillon (Mayo, Fine Gael)
Link to this: Individually | In context | Oireachtas source
715. To ask the Minister for Education and Skills to provide an update on the capital delivery of a building extension at a secondary school (details supplied) in County Mayo; the current stages completed and outstanding within the project life cycle for delivery of this permanent building; and if she will make a statement on the matter. [38804/23]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
I am pleased to advise the Deputy that approval for additional bespoke modular accommodation comprising of 7 x 60m2 mainstream classrooms, 5 x Special Education Tuition rooms, 1 x Art room, 1 x Science room + prep area together with the reconfiguration of an existing space to provide accommodation for a Special Educational Needs class has issued to the School Authority in question. The Special Educational Needs classroom is due for handover to the School Authority next week.
The project is being delivered under my Department’s Devolved SEN Reconfiguration and Modular Accommodation programme. This programme provides project management supports to enable the accommodation to be provided as quickly as possible and helps to ease the administrative workload for individual schools in relation to the management and delivery of the project.
The use of my Department's Modular Accommodation Framework also assists in ensuring lead in periods for procurement of modular accommodation are minimised to the greatest extent possible.
The overall construction sector environment is challenging and my Department and the Project Management Company are doing everything possible to ensure that modular accommodation is delivered as quickly as possible. My Department is fully aware of the urgency in respect of same and will be working with the School Authority to keep it updated on overall project delivery and timelines.
The modular project, at the school in question, is progressing as per programme. The overall modular design is agreed with the necessary statutory applications expected to be lodged over the next fortnight, with the contractor expected to commence on site in late September. The School Authority has overall responsibility for the delivery of this project.