Written answers
Tuesday, 11 July 2023
Department of Transport, Tourism and Sport
Rail Network
John Lahart (Dublin South West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
182. To ask the Minister for Transport, Tourism and Sport the total cost to date of the Metrolink North project; and if he will make a statement on the matter. [34289/23]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
The total spend on the Metro North project until the end of 2014 was €166m. €67m of this expenditure can be considered as lasting value expenditure that is still required for the current MetroLink project. Of the other €99m, approximately €28m was related to Railway Procurement Agency (RPA) staff and associated expense costs.
At the end of June 2023, a total of circa €121m has been invested in MetroLink.
John Lahart (Dublin South West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
183. To ask the Minister for Transport, Tourism and Sport the total cost to date of the Metrolink Southwest project; and if he will make a statement on the matter. [34291/23]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
The NTA has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area. Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a direct reply on the specific issue raised. Please contact my private office if you do not receive a reply within 10 days.