Written answers
Tuesday, 27 June 2023
Department of Housing, Planning, and Local Government
Housing Provision
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
346. To ask the Minister for Housing, Planning, and Local Government for an update on the revised social housing construction and acquisition caps for local authorities and AHBs under the social housing investment programme; and if he will set out the methodology and time period used in determining the caps and revised caps. [30602/23]
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
347. To ask the Minister for Housing, Planning, and Local Government the average cost of buy-and-renew social homes delivered in Dublin city and county in 2022 and to date in 2023. [30603/23]
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
348. To ask the Minister for Housing, Planning, and Local Government the average cost of tenant in situ purchases in Dublin city and county in 2022 and to date in 2023. [30604/23]
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
349. To ask the Minister for Housing, Planning, and Local Government the total capitalisation provided to the LDA to date; the LDA's total borrowing capacity; and the plans the Government intends to make regarding these arrangements. [30611/23]
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
350. To ask the Minister for Housing, Planning, and Local Government the average unit cost of social housing acquisitions acquired in 2022 and separately to date in 2023; and to provide a breakdown of average costs, by size of unit, and by vacant unit versus tenant in situ acquisitions. [30612/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
351. To ask the Minister for Housing, Planning, and Local Government if the targets set out in appendix 1 of Laying the Foundations: Housing Actions Report, produced in 2016 by the then Department of Environment, Community and Local Government, were met in respect of Dublin City Council; and the final spend on same. [30653/23]
Darragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
My Department publishes comprehensive programme level statistics on a quarterly basis on social housing delivery activity by local authorities and Approved Housing Bodies (AHBs) in each local authority. This data is available to the end of 2022, and is published on the statistics page of my Department’s website, at the following link: www.gov.ie/en/collection/6060e-overall-social-housing-provision/
The total funding provided by my Department to Dublin City Council for the delivery of capital and current housing programmes for the period 2015 to 2017 is set out in the table below.
Local Authority | Capital €m | Current €m | Total €m |
---|---|---|---|
Dublin City Council | 376 | 347 | 723 |
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
352. To ask the Minister for Housing, Planning, and Local Government if the 62 local authority housing units approved for construction in a location (details supplied) in May 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30654/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
353. To ask the Minister for Housing, Planning, and Local Government if the 35 local authority housing units approved for construction in a location (details supplied) in May 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30655/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
354. To ask the Minister for Housing, Planning, and Local Government if the 30 local authority housing units approved for construction at a location (details supplied) in May 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30656/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
355. To ask the Minister for Housing, Planning, and Local Government if the 30 local authority housing units approved for construction at a location (details supplied) in May 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30657/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
356. To ask the Minister for Housing, Planning, and Local Government if the 19 AHB housing units approved for construction at a location (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30658/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
357. To ask the Minister for Housing, Planning, and Local Government if the 23 AHB housing units approved for construction at a location (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30659/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
358. To ask the Minister for Housing, Planning, and Local Government if the 20 AHB housing units approved for construction at a location (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30660/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
359. To ask the Minister for Housing, Planning, and Local Government if the eight AHB housing units approved for construction at a location (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30661/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
360. To ask the Minister for Housing, Planning, and Local Government if the 15 AHB housing units approved for construction at a location (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30662/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
361. To ask the Minister for Housing, Planning, and Local Government if the 12 local authority housing units approved for construction at a location (details supplied) in January 2016 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30663/23]
Aodhán Ó Ríordáin (Dublin Bay North, Labour)
Link to this: Individually | In context | Oireachtas source
362. To ask the Minister for Housing, Planning, and Local Government if the 16 local authority housing units approved for construction at a location (details supplied) in January 2016 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [30664/23]
No comments