Written answers

Tuesday, 23 May 2023

Department of Education and Skills

Schools Building Projects

Photo of Paul McAuliffePaul McAuliffe (Dublin North West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

318. To ask the Minister for Education and Skills the status of a new build for a school (details supplied). [24783/23]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The major building project for the school referred to by the Deputy is being delivered under my Department's ADAPT Programme.

The ADAPT Programme uses a professional external Project Manager to co-ordinate and drive the Design Team to achieve the best possible timeframe for the project through the stages of Architectural Planning to Tender and Construction.

The project is currently at an advanced stage of Architectural Planning – Stage 2(b) – Detailed Design, where the Design Team make the applications for all Statutory Approvals, and prepare the suite of tender documents.

All Statutory Approvals have been secured, and my department is currently reviewing the design team submission of the Stage 2(b) Report.

Upon completion of the review and subsequent approval, my Department will be in further contact with the school authority and design team.

Comments

No comments

Log in or join to post a public comment.