Written answers

Wednesday, 10 May 2023

Department of Housing, Planning, and Local Government

Housing Provision

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

115. To ask the Minister for Housing, Planning, and Local Government if the 14 AHB housing units under an association (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reason for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [22072/23]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

This project proposal was not advanced by the AHB in question. Instead, it was advanced by Wexford County Council who reported it as completed in Q3 2019 with 10 new social homes delivered.

This project received funding of over €2.3 million from my Department.

There was no official opening of the project.

My Department publishes quarterly Social Housing Construction Projects Status Reports (CSR), which provide details of social housing developments that have been completed, are under construction or are progressing through the various stages of design and tender processes.  The CSR, setting out the position at end Q3 2019, can be found on my Department’s website at the following link:  

SHCP Status Report Q3 2019

The full set of published CSRs can be found at the following link:

www.gov.ie/en/collection/cb885-social-housing-construction-projects-status-reports/

Photo of Brendan HowlinBrendan Howlin (Wexford, Labour)
Link to this: Individually | In context | Oireachtas source

116. To ask the Minister for Housing, Planning, and Local Government if the 16 AHB housing units under an association (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reason for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [22073/23]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Following my Department providing initial approval in principle for this project in July 2015, I understand from Wexford County Council that it was unable to proceed at that time as it could not obtain a discharge license to cover the site due to issues with waste water in the area.  I further understand that the Council and AHB are now hopeful these issues are being addressed and they will look to re-commence the project.

I am happy to continue my Department's funding support for the project on the basis that the previous issues can be overcome and the development can move forward as soon as possible.

Further information on the project should be available directly from Wexford County Council. 

Photo of Alan KellyAlan Kelly (Tipperary, Labour)
Link to this: Individually | In context | Oireachtas source

117. To ask the Minister for Housing, Planning, and Local Government if the nine AHB housing units in an area (details supplied) in July 2015 have finished construction; if so, the projected completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reason for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [22076/23]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Tipperary County Council reported this projected as completed in Q4 2022 for nine new social homes. 

This project received funding of just over €2 million from my Department.

I officially opened this housing development on 20 February 2023.

My Department publishes quarterly Social Housing Construction Projects Status Reports (CSR), which provide details of social housing developments that have been completed, are under construction or are progressing through the various stages of design and tender processes. The CSR setting out the position at end Q4 2022 can be found on my Department’s website at the following link:

SHCP - Status Report Q4 2022

The full set of published CSR reports can be found at this link:

Photo of Alan KellyAlan Kelly (Tipperary, Labour)
Link to this: Individually | In context | Oireachtas source

118. To ask the Minister for Housing, Planning, and Local Government if the seven AHB housing units under an organisation (details supplied) in July 2015 have finished construction; if so, the projected completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reason for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [22092/23]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

My Department was notified by the local authority that the AHB involved in these proposed sheltered housing projects subsequently decided not to advance them.  

As the sites were owned by the AHB, the local authority did not have the option to develop them directly.

Photo of Alan KellyAlan Kelly (Tipperary, Labour)
Link to this: Individually | In context | Oireachtas source

119. To ask the Minister for Housing, Planning, and Local Government if the five local authority housing units approved for construction in an area (details supplied) in May 2015 have finished construction; if so, the projected completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reason for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [22093/23]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Tipperary County Council reported this project as completed in Q3 2020 for 5 new social homes.

This project received funding of €1.15 million from my Department.

The project was not formally opened by a Minister.

My Department publishes quarterly Social Housing Construction Projects Status Reports (CSR), which provide details of social housing developments that have been completed, are under construction or are progressing through the various stages of design and tender processes. The CSR setting out the position at end Q3 2020 can be found on my Department’s website at the following link:

SHCP - Status Report Q3 2020

The full set of published CSR reports can be found at this link:

Photo of Duncan SmithDuncan Smith (Dublin Fingal, Labour)
Link to this: Individually | In context | Oireachtas source

120. To ask the Minister for Housing, Planning, and Local Government if the 22 AHB housing units under an association (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reason for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [22096/23]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

My Department gave funding approval under the CALF Scheme for the project referenced.  Approval for 43 social housing homes was given in 2017, with additional funding for a further 22 social housing homes approved in 2019. 65 homes were completed in December 2021. The total cost of the project was €15,619,980 with CALF funding approved by my Department of €3,674,138. The project was officially opened by the Tánaiste Micheál Martin on 1 November 2022.

My Department publishes quarterly Social Housing Construction Projects Status Reports (CSR), which provide details of social housing developments that have been completed, are under construction or are progressing through various stages of design and tender processes.  The CSR, setting out the position at end Q4 2021, can be found on my Department's website at the following link:  

The full set of published CSRs can be found at this link:

Photo of Pa DalyPa Daly (Kerry, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

121. To ask the Minister for Housing, Planning, and Local Government if he can advise when the following single dwelling rural house will begin construction and completion for a person (details supplied). [22106/23]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Awaiting reply from Department.