Schools Building Projects

Photo of Mark WardMark Ward (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

124. To ask the Minister for Education and Skills the action her Department is taking to ensure a project in a school in Rathcoole (details supplied) is delivered at the earliest opportunity given the many delays already faced and the pressing need for increased capacity to cater for secondary school students in the Newcastle and Rathcoole areas; and if she will make a statement on the matter. [14198/23]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The Large scale capital project for the school referred to by the Deputy is at an advanced stage of Architectural Planning Stage 3 – tender action and award.  The project brief includes the Demolition of the existing school and the phased construction of a three storey 1000 pupil Community School with Special Education Needs Unit and PE Hall.  The project is currently on hold to proceed to construction due to capital funding pressures.

My Department's Planning and Building Unit is currently assessing its work programme and priorities for 2023 in the context of its available funding.  My Department's published NDP allocation for 2023 is €860 million.  High construction inflation remains a continuing feature of the construction sector for 2023.  As part of its planning ahead for the remainder of 2023, my Department is engaging with the Department of Public Expenditure, NDP Delivery and Reform in relation to capital funding pressures in order to continue to adequately support the operation of the school system with rollout of school building projects to construction in 2023. 

I want to reassure the Deputy and the relevant school communities that school building projects that are currently on hold due to capital funding pressures will be progressed and delivered – it is a question of timing.  I am well aware of the urgency in getting these projects delivered as quickly as possible.  The outcome of our engagement with the Department of Public Expenditure, NDP Delivery and Reform will provide better clarity on the timelines for the progression of these projects. This is a key priority for me.  I have engaged directly with Minister Donohue on this matter and will continue to do so with a view to getting our funding pressures resolved as quickly as possible.   

We will be providing an update to individual schools when our engagement with the Department of Public Expenditure, NDP Delivery and Reform concludes.  In tandem with this, my Department’s Planning & Building Unit will also be updating Patron Bodies and School Management Bodies at that stage. Key priorities for my Department's work programme include continuing strong delivery to support the operation of the school system with particular regard to planning ahead for the 2023/24 school year. 