Department of Housing, Planning, and Local Government
Housing Schemes
Noel Grealish (Galway West, Independent)
Link to this: Individually | In context | Oireachtas source
232. To ask the Minister for Housing, Planning, and Local Government the number of affordable and social houses that are due to be completed within the next two years, by local authority; the number of affordable and social houses completed in the past two years, by each local authority area; the number of affordable and social houses for which planning permission is currently sought; the projected dates of completion, by each local authority area; and if he will make a statement on the matter. [60102/22]
Darragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
Housing for All is the Government’s plan to increase the supply of housing to an average of 33,000 per year over the next decade. This includes the delivery of 90,000 social homes, 36,000 affordable purchase homes and 18,000 cost rental homes. Housing for All is supported by an investment package of over €4bn per annum, through an overall combination of €12bn in direct Exchequer funding, €3.5bn in funding through the Land Development Agency and €5bn funding through the Housing Finance Agency.
Under Housing for All, the Government will deliver 47,600 new build social homes; 3,500 social homes through long-term leasing and 28,500 new affordable homes in the period 2022-2026.
The below table sets out the targets under Housing for All for the next two years by local authority.
- | Target 2023 Build & Lease | Target 2023 Lease | Target 2023 Build | Target 2024 Build & Lease | Target 2024 Lease | Target 2024 Build |
---|---|---|---|---|---|---|
Carlow | 90 | 90 | 92 | 92 | ||
Cavan | 80 | 80 | 82 | 82 | ||
Clare | 149 | 149 | 153 | 153 | ||
Cork County | 622 | 622 | 636 | 636 | ||
Cork City | 607 | 71 | 536 | 598 | 50 | 548 |
Donegal | 155 | 155 | 159 | 159 | ||
Dublin City | 2406 | 475 | 1931 | 2384 | 410 | 1974 |
DLR | 403 | 39 | 364 | 472 | 100 | 372 |
Fingal | 850 | 160 | 690 | 825 | 120 | 705 |
Galway County | 351 | 351 | 358 | 358 | ||
Galway City | 219 | 219 | 224 | 224 | ||
Kerry | 261 | 261 | 267 | 267 | ||
Kildare | 486 | 86 | 400 | 409 | 409 | |
Kilkenny | 149 | 149 | 153 | 153 | ||
Laois | 79 | 79 | 80 | 80 | ||
Leitrim | 26 | 26 | 26 | 26 | ||
Limerick | 502 | 502 | 513 | 513 | ||
Longford | 74 | 74 | 76 | 76 | ||
Louth | 156 | 156 | 160 | 160 | ||
Mayo | 151 | 151 | 154 | 154 | ||
Meath | 323 | 80 | 243 | 249 | 249 | |
Monaghan | 56 | 56 | 57 | 57 | ||
Offaly | 67 | 67 | 68 | 68 | ||
Roscommon | 47 | 47 | 48 | 48 | ||
Sligo | 111 | 111 | 114 | 114 | ||
South Dublin | 793 | 90 | 703 | 838 | 120 | 718 |
Tipperary | 155 | 155 | 158 | 158 | ||
Waterford | 255 | 46 | 209 | 214 | 214 | |
Westmeath | 124 | 124 | 126 | 126 | ||
Wexford | 172 | 172 | 176 | 176 | ||
Wicklow | 379 | 153 | 226 | 231 | 231 | |
Total | 10,300 | 1,200 | 9,100 | 10,100 | 800 | 9,300 |
A key action of Housing for All is that local authorities developed and submitted Housing Delivery Action Plans. The Plans set out details of both social and affordable housing delivery as appropriate over the period 2022 - 2026. All local authorities submitted their Housing Delivery Action Plans to me in December and my Department has worked closely with the local authorities to review and finalise the Plans, having regard to the targets and policy objectives set out in Housing for All. The Plans have been published by each local authority on their own website.
My Department publishes comprehensive programme level statistics on a quarterly basis on social housing delivery activity in all local authorities. This data is available until the end of Quarter 2 2022 and is published on the statistics page of my Department’s website, at the following link: www.gov.ie/en/collection/6060e-overall-social-housing-provision/.
My Department also publishes the Social Housing Construction Status Report (CSR). The CSR provides details of social housing developments which have been completed, are under construction or are progressing through the various stages of the design and pre-tender process. The most recent publication was for Q2 2022. The report is available at the following link: www.gov.ie/en/publication/5a259-social-housing-construction-projects-status-report-q2-2022/.
This year represents the first year of a very ambitious programme of delivery of affordable housing and significant funding has been secured and is being made available to support delivery of affordable housing for purchase or for cost rental through the various delivery streams.
Local authorities have begun collating information on the delivery of affordable homes in their area in the same manner as is currently undertaken for social housing. It is intended that information on delivery across all delivery streams will be coordinated by my Department and I expect that my Department will be in a position to commence reporting on affordable delivery figures in national quarterly delivery statistics before year-end.
My Department does not collate information on the number of planning permissions being sought in relation to social and affordable housing developments. This information may be available from individual local authorities.
Noel Grealish (Galway West, Independent)
Link to this: Individually | In context | Oireachtas source
233. To ask the Minister for Housing, Planning, and Local Government the number of houses in new developments purchased by local councils and housing agencies in each of the past three years, broken down by local authority area; the number of houses purchased by local councils and housing agencies in new developments, where such purchases represented 50% or more of the total development, by council area; and if he will make a statement on the matter. [60103/22]
Darragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
My Department publishes the Social Housing Construction Status Report (CSR). The CSR provides details of social housing developments, including details of turnkey delivery, which have been completed, are under construction or are progressing through the various stages of the design and pre-tender process. The most recent publication was for Q2 2022. The report is available at the following link: www.gov.ie/en/publication/5a259-social-housing-construction-projects-status-report-q2-2022/.
A version of the CSR file can also be downloaded for analysis at the link below: data.gov.ie/dataset/social-housing-construction-status-report-q2-2022?package_type=dataset.
For some projects, a local authority or Approved Housing Body will enter into a development agreement, prior to the commencement of construction, for the purchase of homes for social or affordable housing. My Department does not hold the details requested by the Deputy in relation to the number of projects where such arrangements involve over 50% of the overall development.