347. To ask the Minister for Education and Skills the outcome of the stage one report on the campus project at Clonard, County Wexford; the work that has progressed on the provision of the two schools on the site since this stage one report was reviewed; if there is any other update on both schools on the campus; and if she will make a statement on the matter. [56535/22]
Norma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source
The project referred to by the deputy is a campus project for two schools in Wexford. It has been devolved for delivery to Waterford and Wexford Education and Training Board (WWETB).
The Department recently received the final Stage 1 Report, by means of follow-up to the Stage 1 meeting held with WWETB and its Design Team. The Department is engaging with WWETB in relation to the options for progressing the delivery of both schools.
While it is not possible to provide a timeline for completion of the project at this early stage, WWETB will be engaging directly with the school authorities to keep them informed of progress