447. To ask the Minister for Education and Skills the number of school building projects currently in-hand in County Kildare at primary or second level; the expected dates of completion for each project; and if she will make a statement on the matter. [50293/22]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Under Project Ireland 2040, the education sector will receive a total of approximately €4.4 billion capital investment over the period 2021-2025. This significant investment allows us to move forward with certainty on our ambitious plans and deliver high quality building projects, with a real focus on sustainability, for school communities across Ireland. This investment will build on the good progress being made on adding capacity to cater for demographic changes and provision for children with special educational needs. This investment will also facilitate an increased focus on the modernisation of existing school stock and help transition the school system for an era of net zero carbon by 2050.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. Most of which are expected to be either under construction or completed in the period up to 2025.

During the period 2018 to 2021 691 school building projects were completed under the Large Scale Capital Programme (LSCP) and the Additional School Accommodation Scheme (ASA). These projects delivered in excess of 64,000 school places.

There are approximately 1,300 school building projects currently in progress across the various stages of planning, design, tender and construction under the Large Scale and Additional School Accommodation Scheme, of which 48 school building projects are in County Kildare. Most of these projects are expected to be either under construction or completed in the period 2022 to 2025.

The current status of all projects are listed on a county by county basis at www.gov.ie. and is updated on a regular basis to reflect their progress through the various stages of capital appraisal, site acquisition, design, tender and construction.

This also lists all school building projects completed under the Large Scale and Additional Accommodation Scheme, in county order, from 2010 to date.

Photo of Bernard DurkanBernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

448. To ask the Minister for Education and Skills the progress to date in relation to the three-school project at Hazelhatch, Celbridge, County Kildare, incorporating a replacement school (details supplied) which is now an urgent requirement and two other schools on a single site; if all the necessary road and realignment works have been completed by the local authority to facilitate this progress; when construction work will start in respect of each of the schools; and if she will make a statement on the matter. [50294/22]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The project to which the Deputy refers has been devolved to the National Development Finance Agency (NDFA) for delivery as part of a programme of school building projects.

A letter was issued by the Department to the schools earlier this year to advise that their respective school had been included in the programme. The NDFA has since been in contact with each school to introduce the team, communicate arrangements and discuss the project briefs.

The next step is for the NDFA to procure a Design Team for the project bundle to progress the projects through the design stages. An estimated timeline for the completion of the project will be available once the design stages have concluded.