Department of Housing, Planning, and Local Government

Planning Issues

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

178. To ask the Minister for Housing, Planning, and Local Government the number of un-commenced Part 8 planning permissions for residential units that have been granted by local authorities and the number of units in each application that are to be considered within each local authority in each of the years since 2011 to 2021 and to date in 2022, in tabular form. [47069/22]

Photo of Peter BurkePeter Burke (Longford-Westmeath, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The Department does not maintain information on un-commenced Part 8 planning permissions from the local authorities. We do, however, publish a range of information on the advancement of social housing programmes broken down by local authority.

This includes programme level statistics on a quarterly basis on social housing delivery by the local authorities, with data up to the end of Quarter 1 of 2022 available on the statistics page of my Department’s website at the following link:

www.gov.ie/en/collection/6060e-overall-social-housing-provision/.

My Department also publishes a Social Housing Construction Status Report (CSR) each quarter. This provides details of social housing developments that have been completed, are under construction or are progressing through the various stages of the design and pre-tender process for each local authority. The data to Quarter 1 of 2022 is available at the following link:

www.gov.ie/en/publication/6912a-social-housing-construction-projects-status-report-q1-2022/.

The Quarter 2 statistics are being collated and will be published in due course.

The information in the CSR on social housing developments at the various stages of advancement includes those that are at the 'pre-planning' stage/Stage 2. Developments beyond that stage will have secured planning approval.

Projects that are at Stage 4 and beyond have been approved by my Department to appoint contractors. I look forward to seeing those homes completed, and allocated, to families and individuals on the waiting lists, as soon as possible.