Written answers

Tuesday, 20 September 2022

Department of Education and Skills

Technological Universities

Photo of Matt ShanahanMatt Shanahan (Waterford, Independent)
Link to this: Individually | In context | Oireachtas source

437. To ask the Minister for Education and Skills if he will provide a schedule of the dates of each of the project milestones with respect to the Coonagh Campus development undertaken by Limerick Institute of Technology / Technological University of the Shannon since the project's inception. [45509/22]

Photo of Matt ShanahanMatt Shanahan (Waterford, Independent)
Link to this: Individually | In context | Oireachtas source

438. To ask the Minister for Education and Skills if he will provide a schedule of formal correspondence between the Department, the Higher Education Authority and Limerick Institute of Technology / Technological University of the Shannon with respect to the Coonagh Campus development undertaken by LIT/TUS since the project's inception. [45510/22]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 437 and 438 together.

As the Deputy will be aware, in accordance with the Public Spending Code, the Project Lifecycle refers to the series of steps and activities which are necessary to take the proposal from concept to completion and evaluation.

The Coonagh Campus project was split into two components; the ‘Enabling / Shell & Core’ works and the 'Fit out' works. I have set out the main stages and dates in the table below in respect of each of these components.

Project Element Tender Commencement Construction Commencement Construction Completion Project Review & Reporting Period
Enabling Shell & Core July 2017 July 2018 February 2020 February 2023
Fit Out TBC TBC TBC TBC

The table attached sets out the key communications and milestones relating to the project at TUS-Coonagh Campus, from the decision to acquire the site up to the current Fit Out phase of the project. It is important to note that since the inception of the TUS-Coonagh Project and between the milestone dates referenced in the table there was extensive engagement between the Institute, HEA DFHERIS, resolution of queries in relation to procurement, tendering, etc. However given the volume of these and the timeframe required to respond my Department have focused on the key milestones of the project.

Documents/Key Milestones Date
Approval of site purchase at cost of €3.5m Nov 2015
Economic Impact of LIT Campus Report June 2016
ABP grant planning July 2017
Procurement process commenced for the ‘Enabling / Shell & Core Contract’ July 2017
DES Approval for development project June 2018
Contract awarded for ‘Enabling Shell and Core contract’ by LIT and commenced onsite July 2018
The Enabling Shell and Core contract’contract reached substantial completion February 2020
HEA Options and Recommendations Report submitted to DFHERIS for fit-out phase Dec 2020
DFHERIS approval for Fit-out commencement May 2022

Photo of Matt ShanahanMatt Shanahan (Waterford, Independent)
Link to this: Individually | In context | Oireachtas source

439. To ask the Minister for Education and Skills if he will provide a schedule of the funding made available to the Coonagh Campus development undertaken by Limerick Institute of Technology / Technological University of the Shannon since the project's inception to include a breakdown by date, value and purpose of all current and capital exchequer funding. [45511/22]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The information requested by the Deputy is set out below.

Payment Date Amount Detail
2017 €3,500,000.00 Site Acquisition
2019 €5,364,014.24 Enabling Shell & Core Works & Design Team Fees
2020 €288,725.85 Enabling Shell & Core Works & Design Team Fees

Photo of Matt ShanahanMatt Shanahan (Waterford, Independent)
Link to this: Individually | In context | Oireachtas source

440. To ask the Minister for Education and Skills if he will provide a schedule of the dates of each of the project milestones with respect to the acquisition of Crowley Park by Galway Mayo Institute of Technology / Atlantic Technological University since the project’s inception. [45512/22]

Photo of Matt ShanahanMatt Shanahan (Waterford, Independent)
Link to this: Individually | In context | Oireachtas source

441. To ask the Minister for Education and Skills if he will provide a schedule of formal correspondence between the Department, the Higher Education Authority and Galway Mayo Institute of Technology / Atlantic Technological University with respect to the Crowley Park development undertaken by GMIT/ATU since the project's inception. [45513/22]

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I propose to take Questions Nos. 440 and 441 together.

GMIT’s interest in the acquisition of Crowley Park, and its engagement with the Higher Education Authority (HEA), the Department of Further and Higher Education, Research, Innovation and Science and previously the Department of Education and Skills, extended back many years prior to its eventual acquisition of the property in December 2021.

Approval was provided to acquire the site in 2018; however, the GMIT bid at that time was ultimately not successful.

The table beneath sets out key communications and milestones relating to the successful acquisition which was eventually finalised in December 2021. It is important to note that between the milestone dates referenced in the table there was extensive background work and engagement between the parties, including engagements between GMIT and the vendor, updating of valuations, resolution of queries etc. The COVID-19 pandemic and steps to be followed on the side of the vendor also had an impact on overall timelines.

Document/Milestone Date
Business case submitted by GMIT to HEA May 2019
HEA recommendation to Department of Education and Skills July 2019
Queries issue to HEA from Department of Education and Skills July 2019
Further communication and supporting documents from GMIT to HEA July 2020
Further supporting documents from GMIT to HEA November 2020
Communication between HEA and DFHERIS on proposal November 2020
New business case submitted by GMIT February 2021
GMIT reply to outstanding queries February 2021
Approval by Minister for Further and Higher Education, Research, Innovation and Science February 2021
Feedback from Department of Public Expenditure and Reform March 2021
Approval letter issued to HEA March 2021
Acquisition concluded by GMIT December 2021

Comments

No comments

Log in or join to post a public comment.